BALAJI PARK

by AYAZ AHMED MOHOMMEDALI KABADI · Panvel, Raigarh

Registered on MahaRERA under P52000024340. Status: Lapsed (registration period ended). Its completion date has moved from March 2023 to June 2025, 27 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2025) has passed.

GharKundli’s full report on BALAJI PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000024340
Status
Lapsed (registration period ended)
Builder
AYAZ AHMED MOHOMMEDALI KABADI
Location
Panvel, Raigarh · 410206
Project type
Others
Registered on
5 Feb 2020
Completion date at registration
March 2023
Latest completion date
June 2025
Delay so far
27 months
Homes
29
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

BALAJI PARK: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about BALAJI PARK

Is BALAJI PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), BALAJI PARK is registered as P52000024340 and its status is "Lapsed (registration period ended)".

Where is BALAJI PARK?

BALAJI PARK by AYAZ AHMED MOHOMMEDALI KABADI is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000024340, per GharKundli's check of MahaRERA records.

When is possession of BALAJI PARK due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BALAJI PARK in Panvel, Raigarh is 30 June 2025 — 27 months later than 30 March 2023, the date given at registration. That date has already passed.

Does BALAJI PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of BALAJI PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AYAZ AHMED MOHOMMEDALI KABADI.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.