GANA RESIDENCY

by TRILLION SQUARE DEVELOPERS LLP · Pushpak New, Raigarh

Registered on MahaRERA under P52000026641. Status: Lapsed (registration period ended). Its completion date has moved from June 2023 to December 2025, 30 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

GharKundli’s full report on GANA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000026641
Status
Lapsed (registration period ended)
Builder
TRILLION SQUARE DEVELOPERS LLP
Location
Pushpak New, Raigarh · 410206
Project type
Others
Registered on
12 Oct 2020
Completion date at registration
June 2023
Latest completion date
December 2025
Delay so far
30 months
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

GANA RESIDENCY: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about GANA RESIDENCY

Is GANA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GANA RESIDENCY is registered as P52000026641 and its status is "Lapsed (registration period ended)".

Where is GANA RESIDENCY?

GANA RESIDENCY by TRILLION SQUARE DEVELOPERS LLP is in Pushpak New, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000026641, per GharKundli's check of MahaRERA records.

When is possession of GANA RESIDENCY due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GANA RESIDENCY in Pushpak New, Raigarh is 31 December 2025 — 30 months later than 30 June 2023, the date given at registration. That date has already passed.

Does GANA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of GANA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRILLION SQUARE DEVELOPERS LLP, which has 2 other projects registered on MahaRERA.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.