Skip to content
GharKundli

Sai Meher

by Prasad Developers · Pushpak New, Raigarh

Registered on MahaRERA under P52000028509. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on Sai Meher

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000028509
Status
Completed
Builder
Prasad Developers
Location
Pushpak New, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
8 Mar 2021
Completion date at registration
June 2024
Latest completion date
June 2024
Homes
27
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

Sai Meher: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Meher

Is Sai Meher registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Meher is registered as P52000028509 and its status is "Completed".

Where is Sai Meher?

Sai Meher by Prasad Developers is in Pushpak New, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000028509, per GharKundli's check of MahaRERA records.

When is possession of Sai Meher due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Meher in Pushpak New, Raigarh is 30 June 2024.

Does Sai Meher have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in Sai Meher?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Meher has 27 homes in 1 tower registered on MahaRERA.

When was Sai Meher registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Meher was registered on MahaRERA on 8 March 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Meher?

No court cases are listed for Sai Meher on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Meher?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Prasad Developers, which has 1 other project registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.