by M/S SAPPHIRE INFRA · Khopoli, Raigarh
Registered on MahaRERA under P52000051640, and currently active. Its completion date has moved from July 2025 to November 2027, 28 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Sapphire Infra
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000051640
- Status
- Registered and active
- Builder
- M/S SAPPHIRE INFRA
- Location
- Khopoli, Raigarh · 410203
- Project type
- Residential / Group Housing
- Registered on
- 27 Jun 2023
- Completion date at registration
- July 2025
- Latest completion date
- November 2027
- Delay so far
- 28 months
- Homes
- 36
- Sold or booked
- 22%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
Sapphire Infra: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Sapphire Infra
Is Sapphire Infra registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sapphire Infra is registered as P52000051640 and its status is "Registered and active".
Where is Sapphire Infra?
Sapphire Infra by M/S SAPPHIRE INFRA is in Khopoli, Raigarh (pincode 410203), Maharashtra, and is registered on MahaRERA as P52000051640, per GharKundli's check of MahaRERA records.
When is possession of Sapphire Infra due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sapphire Infra in Khopoli, Raigarh is 30 November 2027 — 28 months later than 31 July 2025, the date given at registration.
Does Sapphire Infra have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Sapphire Infra?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S SAPPHIRE INFRA.
Other projects in pincode 410203
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.