Gajanan Vatika Residency Building -2

by M/S. WONDER HOMES · Khopoli, RaigarhAlso near Shilphata

Possession: Gajanan Vatika Residency Building -2 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000021347. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Gajanan Vatika Residency Building -2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Gajanan Vatika Residency Building -2 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000012882)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons, particularly the pandemic of Covid-19. We have the c…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons, particularly the pandemic of Covid-19. We have the consent of 66.67% of allottees for purpose of extension of RERA registration period of the said project.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000025408)

    Reason the builder gave MahaRERA:
    “We sincerely apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen issues with procurement, unexpected site conditions, and coordination challenges. Despite the…” Read the full reason“We sincerely apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen issues with procurement, unexpected site conditions, and coordination challenges. Despite these setbacks, we are diligently working to address these challenges and to complete the remaining work. Currently, 78% of the project has been completed. We are in the final stages and intend to apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring the progress and are taking all necessary steps to ensure the ti…”
  4. 30 November 2026

    Extended at the builder's request (MahaRERA application EA23072621843)

    Reason the builder gave MahaRERA:
    “we, M/s. Wonder Homes, hereby declare the following with respect to the project Gajanan Vatika Residency Building -2 bearing registration number P52000021347 registered under MahaRERA. The delay in the completion of the real estate project…” Read the full reason“we, M/s. Wonder Homes, hereby declare the following with respect to the project Gajanan Vatika Residency Building -2 bearing registration number P52000021347 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 15-05-2026 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-u…”

Source: Gajanan Vatika Residency Building -2’s extension records on MahaRERA (P52000021347), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gajanan Vatika Residency Building -2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000021347
Status
Completed
Builder
M/S. WONDER HOMES
Location
Khopoli, Raigarh · 410203
Project type
Residential / Group Housing
Registered on
24 Jun 2019
Completion date at registration
December 2022
Latest completion date
November 2026
Delay so far
47 months
Homes
95
Sold or booked
21%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Gajanan Vatika Residency Building -2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Gajanan Vatika Residency Building- 2100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Gajanan Vatika Residency Building- 2: covers 8 (G+7)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gajanan Vatika Residency Building -2 every month.

Gajanan Vatika Residency Building -2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Gajanan Vatika Residency Building- 2 (8 floors, 95 units)
  • Land: 3,880 sq m (about 1.0 acres) · sanctioned built-up 4,936 sq m

The builder’s record and reviews

Wonder Homes has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 32 months). No complaints on MahaRERA.

Read Google reviews of Gajanan Vatika Residency Building -2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gajanan Vatika Residency Building -2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gajanan Vatika Residency Building -2

What is the possession date of Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gajanan Vatika Residency Building -2 in Khopoli, Raigarh is 30 November 2026 — 47 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Gajanan Vatika Residency Building -2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gajanan Vatika Residency Building -2's builder has filed on MahaRERA, the official one, is 30 November 2026, already 47 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gajanan Vatika Residency Building -2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons, particularly the pandemic of Covid-19. We have the consent of 66.67% of allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "We sincerely apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen issues with procurement, unexpected site conditions, and coordination challenges. Despite these setbacks, we are diligently working to address these challenges and to complete the remaining work. Currently, 78% of the project has been completed. We are in the final stages and intend to apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring the progress and are taking all necessary steps to ensure the ti…"; to 30 November 2026, giving the reason "we, M/s. Wonder Homes, hereby declare the following with respect to the project Gajanan Vatika Residency Building -2 bearing registration number P52000021347 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 15-05-2026 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-u…".

What is the RERA number of Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gajanan Vatika Residency Building -2 in Khopoli, Raigarh is P52000021347.

Is Gajanan Vatika Residency Building -2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 is registered as P52000021347 and its status is "Completed".

What is the construction status of Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2's status on MahaRERA is "Completed". As filed by the builder, slab work on Gajanan Vatika Residency Building- 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Gajanan Vatika Residency Building -2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Gajanan Vatika Residency Building -2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 is registered on MahaRERA as P52000021347, its MahaRERA status is "Completed", its completion date has moved 47 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Gajanan Vatika Residency Building -2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Gajanan Vatika Residency (P52000005219, possession 30 Dec 2021). Check that your agreement names the registration of your own wing.

How can I get updates if Gajanan Vatika Residency Building -2's possession date changes?

The latest dates are on Gajanan Vatika Residency Building -2's MahaRERA page (P52000021347). GharKundli's Kundli Watch sends a free WhatsApp update on Gajanan Vatika Residency Building -2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gajanan Vatika Residency Building -2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 has one building filed: Gajanan Vatika Residency Building- 2 with 8 floors and 95 units.

How big is the land of Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 stands on 3,880 sq m of land (about 1.0 acres), with 4,936 sq m of sanctioned built-up area.

What is the track record of Gajanan Vatika Residency Building -2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Wonder Homes has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 32 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Gajanan Vatika Residency Building -2?

Google Maps has reviews of Gajanan Vatika Residency Building -2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gajanan Vatika Residency Building -2?

Gajanan Vatika Residency Building -2 by M/S. WONDER HOMES is in Khopoli, Raigarh (pincode 410203), near Shilphata, Maharashtra, and is registered on MahaRERA as P52000021347, per GharKundli's check of MahaRERA records.

How many homes are in Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 has 95 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.

When was Gajanan Vatika Residency Building -2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Vatika Residency Building -2 was registered on MahaRERA on 24 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Gajanan Vatika Residency Building -2?

No court cases are listed for Gajanan Vatika Residency Building -2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Gajanan Vatika Residency Building -2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. WONDER HOMES, which has 1 other project registered on MahaRERA.