Possession date of ROYAL RESIDENCY: 31 July 2027, moved from 30 March 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000011059, and currently active. Its completion date has moved from March 2024 to July 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ROYAL RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ROYAL RESIDENCY has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT52000019759)

    Reason the builder gave MahaRERA:
    “Due to unfavourable market conditions & very low bookings (Sale of under construction units) we could not complete the project on or before the 31/03/2024.Hence we request Maharera Authorities to extend the time period for completion of pro…” Read the full reason“Due to unfavourable market conditions & very low bookings (Sale of under construction units) we could not complete the project on or before the 31/03/2024.Hence we request Maharera Authorities to extend the time period for completion of project up to 31/03/2026.”
  3. 31 March 2027

    Extended at the builder's request (MahaRERA application EA26032620383)

    Reason the builder gave MahaRERA:
    “3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2026. However the construction work was delayed due to unfavourable market conditions & low bookings (Sale of under construction u…” Read the full reason“3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2026. However the construction work was delayed due to unfavourable market conditions & low bookings (Sale of under construction units).4. Up till now we have completed 95% of the work of Building-1 of the project as per Architect Certificate enclosed. We expect to complete the pending project work and collect necessary NOC and obtain Occupancy Certificate on or before 31/03/2027.Hence we request Maharera Authorities to grant us necessary extension up to 31/03/2027 for completing th…”
  4. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ROYAL RESIDENCY’s extension records on MahaRERA (P52000011059), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ROYAL RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000011059
Status
Registered and active
Builder
Royal Enterprises
Location
Takai, Raigarh · 410203
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
March 2024
Latest completion date
July 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
133
Sold or booked
40%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of ROYAL RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 1 - A to E100%100%100%95%
BUILDING 20%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING 1 - A to E: covers 5 floors
  • BUILDING 2: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROYAL RESIDENCY every month.

ROYAL RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING 1 - A to E (5 floors, 97 units) · BUILDING 2 (6 floors, 36 units)
  • Land: 5,840 sq m (about 1.4 acres) · sanctioned built-up 5,252 sq m
  • Boundaries filed include: Khopoli pen road and forest

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ROYAL RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ROYAL RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROYAL RESIDENCY

What is the possession date of ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ROYAL RESIDENCY in Takai, Raigarh is 31 July 2027 — 36 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ROYAL RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROYAL RESIDENCY's builder has filed on MahaRERA, the official one, is 31 July 2027, already 36 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ROYAL RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Due to unfavourable market conditions & very low bookings (Sale of under construction units) we could not complete the project on or before the 31/03/2024.Hence we request Maharera Authorities to extend the time period for completion of project up to 31/03/2026."; to 31 March 2027, giving the reason "3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2026. However the construction work was delayed due to unfavourable market conditions & low bookings (Sale of under construction units).4. Up till now we have completed 95% of the work of Building-1 of the project as per Architect Certificate enclosed. We expect to complete the pending project work and collect necessary NOC and obtain Occupancy Certificate on or before 31/03/2027.Hence we request Maharera Authorities to grant us necessary extension up to 31/03/2027 for completing th…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ROYAL RESIDENCY in Takai, Raigarh is P52000011059.

Is ROYAL RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY is registered as P52000011059 and its status is "Registered and active".

What is the construction status of ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ROYAL RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ROYAL RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY is registered on MahaRERA as P52000011059, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROYAL RESIDENCY's possession date changes?

The latest dates are on ROYAL RESIDENCY's MahaRERA page (P52000011059). GharKundli's Kundli Watch sends a free WhatsApp update on ROYAL RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROYAL RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY has 2 buildings filed: BUILDING 1 - A to E with 5 floors and 97 units; BUILDING 2 with 6 floors and 36 units.

How big is the land of ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY stands on 5,840 sq m of land (about 1.4 acres), with 5,252 sq m of sanctioned built-up area.

Where can I read reviews of ROYAL RESIDENCY?

Google Maps has reviews of ROYAL RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ROYAL RESIDENCY?

ROYAL RESIDENCY by Royal Enterprises is in Takai, Raigarh (pincode 410203), Maharashtra, and is registered on MahaRERA as P52000011059, per GharKundli's check of MahaRERA records. Its boundaries filed there include Khopoli pen road and forest.

How many homes are in ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY has 133 homes in 2 towers registered on MahaRERA, and 40% of them are sold or booked.

When was ROYAL RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL RESIDENCY was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ROYAL RESIDENCY?

No court cases are listed for ROYAL RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ROYAL RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Royal Enterprises, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Khalapur

All 211 projects in Shilphata (410203) →

Other projects by Royal Enterprises

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.