by Shirish Khivraj Gadiya · Khalapur, Raigarh

Possession date of Advika Hill City-1: 31 December 2027, moved from 26 August 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PP1270002501985, and currently active. Its completion date has moved from August 2026 to December 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Advika Hill City-1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Advika Hill City-1 has moved

  1. 26 August 2026

    Completion date given when the project was registered

  2. 31 August 2027

    Extended at the builder's request (MahaRERA application EA29082622420)

    Reason the builder gave MahaRERA:
    “The project could not be completed within the stipulated period due to unavoidable delays in various project-related activities, including approvals, statutory compliances, and coordination with concerned authorities. The Promoter has taken…” Read the full reason“The project could not be completed within the stipulated period due to unavoidable delays in various project-related activities, including approvals, statutory compliances, and coordination with concerned authorities. The Promoter has taken necessary steps to complete the remaining work and obtain the required approvals and completion documents. Therefore, an extension of the project registration period is requested to enable completion of the pending formalities and project-related activities.”
  3. 31 December 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Advika Hill City-1’s extension records on MahaRERA (PP1270002501985), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Advika Hill City-1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PP1270002501985
Status
Registered and active
Builder
Shirish Khivraj Gadiya
Location
Khalapur, Raigarh · 410202
Project type
Plotted
Registered on
5 Jan 2026
Completion date at registration
August 2026
Latest completion date
December 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Advika Hill City-1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Commencement certificate (CC), as filed on MahaRERA

Latest CC order on MahaRERA: dated 04/12/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Advika Hill City-1 every month.

Advika Hill City-1: buildings, flats and land, as filed on MahaRERA

  • Land: 43,672 sq m (about 10.8 acres) · recreational space 4,384 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Advika Hill City-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Advika Hill City-1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Advika Hill City-1

What is the possession date of Advika Hill City-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Advika Hill City-1 in Khalapur, Raigarh is 31 December 2027 — 12 months later than 26 August 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Advika Hill City-1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Advika Hill City-1's builder has filed on MahaRERA, the official one, is 31 December 2027, already 12 months later than the 26 August 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Advika Hill City-1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1's builder applied to MahaRERA to extend the completion date once: to 31 August 2027, giving the reason "The project could not be completed within the stipulated period due to unavoidable delays in various project-related activities, including approvals, statutory compliances, and coordination with concerned authorities. The Promoter has taken necessary steps to complete the remaining work and obtain the required approvals and completion documents. Therefore, an extension of the project registration period is requested to enable completion of the pending formalities and project-related activities.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Advika Hill City-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Advika Hill City-1 in Khalapur, Raigarh is PP1270002501985.

Is Advika Hill City-1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1 is registered as PP1270002501985 and its status is "Registered and active".

What is the construction status of Advika Hill City-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Advika Hill City-1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Advika Hill City-1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1 is registered on MahaRERA as PP1270002501985, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Advika Hill City-1's possession date changes?

The latest dates are on Advika Hill City-1's MahaRERA page (PP1270002501985). GharKundli's Kundli Watch sends a free WhatsApp update on Advika Hill City-1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Advika Hill City-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1 stands on 43,672 sq m of land (about 10.8 acres) and 4,384 sq m of recreational open space.

Where can I read reviews of Advika Hill City-1?

Google Maps has reviews of Advika Hill City-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Advika Hill City-1?

Advika Hill City-1 by Shirish Khivraj Gadiya is in Khalapur, Raigarh (pincode 410202), Maharashtra, and is registered on MahaRERA as PP1270002501985, per GharKundli's check of MahaRERA records.

When was Advika Hill City-1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Advika Hill City-1 was registered on MahaRERA on 5 January 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on Advika Hill City-1?

No court cases are listed for Advika Hill City-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Advika Hill City-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shirish Khivraj Gadiya.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 410202

All 29 projects in Khalapur (410202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.