AARVI RESIDENCY
by DHARMPAL OMKARMAL CHOUDHARY · Rees, RaigarhAlso near Khalapur, Mohopada
Possession date of AARVI RESIDENCY: 30 March 2027, moved from 31 December 2025 (11 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000079262, and currently active. Its completion date has moved from December 2025 to March 2027: 11 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AARVI RESIDENCY?
How the possession date of AARVI RESIDENCY has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA31122519175)
Reason the builder gave MahaRERA:
“Our project work got delayed due to uncertain rainy conditions in Maharashtra this year. Also, there was labour shortage in last 3 months due to which work completion was not going as expected and hence work could not be completed within th…” Read the full reason
“Our project work got delayed due to uncertain rainy conditions in Maharashtra this year. Also, there was labour shortage in last 3 months due to which work completion was not going as expected and hence work could not be completed within the completion date estimated earlier. Thus for the completion of the development work within next 6 months, we are applying for extension of the project completion date upto 30/06/2026. As prescribed under circular no 07/2019 dated 08 Feb 2019, the consent of more than 51% of the allottees is enclosed herewith.”30 November 2026
Extended at the builder's request (MahaRERA application EA08092622484)
Reason the builder gave MahaRERA:
“The project finalization work is in process after which application of OC has to be done. The work was delayed due to sudden rise in cost of material and shortage of supply. Thus we need extension upto 30-11-2026 so that finalization work c…” Read the full reason
“The project finalization work is in process after which application of OC has to be done. The work was delayed due to sudden rise in cost of material and shortage of supply. Thus we need extension upto 30-11-2026 so that finalization work can be completed and OC can be received.”30 March 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AARVI RESIDENCY’s extension records on MahaRERA (P52000079262), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AARVI RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000079262
- Status
- Registered and active
- Builder
- DHARMPAL OMKARMAL CHOUDHARY
- Location
- Rees, Raigarh · 410222
- Project type
- Residential / Group Housing
- Registered on
- 25 Feb 2025
- Completion date at registration
- December 2025
- Latest completion date
- March 2027
- Delay so far
- 11 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 24
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AARVI RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AARVI RESIDENCY | 100% | 100% | 90% | 85% |
Commencement certificate (CC), as filed on MahaRERA
- AARVI RESIDENCY: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AARVI RESIDENCY every month.
AARVI RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: AARVI RESIDENCY (6 floors, 24 units)
- Land: 489 sq m (about 0.1 acres) · sanctioned built-up 948 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AARVI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AARVI RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AARVI RESIDENCY
What is the possession date of AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AARVI RESIDENCY in Rees, Raigarh is 30 March 2027 — 11 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AARVI RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AARVI RESIDENCY's builder has filed on MahaRERA, the official one, is 30 March 2027, already 11 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AARVI RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Our project work got delayed due to uncertain rainy conditions in Maharashtra this year. Also, there was labour shortage in last 3 months due to which work completion was not going as expected and hence work could not be completed within the completion date estimated earlier. Thus for the completion of the development work within next 6 months, we are applying for extension of the project completion date upto 30/06/2026. As prescribed under circular no 07/2019 dated 08 Feb 2019, the consent of more than 51% of the allottees is enclosed herewith."; to 30 November 2026, giving the reason "The project finalization work is in process after which application of OC has to be done. The work was delayed due to sudden rise in cost of material and shortage of supply. Thus we need extension upto 30-11-2026 so that finalization work can be completed and OC can be received.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AARVI RESIDENCY in Rees, Raigarh is P52000079262.
Is AARVI RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY is registered as P52000079262 and its status is "Registered and active".
What is the construction status of AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AARVI RESIDENCY is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does AARVI RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AARVI RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY is registered on MahaRERA as P52000079262, its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AARVI RESIDENCY's possession date changes?
The latest dates are on AARVI RESIDENCY's MahaRERA page (P52000079262). GharKundli's Kundli Watch sends a free WhatsApp update on AARVI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AARVI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY has one building filed: AARVI RESIDENCY with 6 floors and 24 units.
How big is the land of AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY stands on 489 sq m of land (about 0.1 acres), with 948 sq m of sanctioned built-up area.
Where can I read reviews of AARVI RESIDENCY?
Google Maps has reviews of AARVI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AARVI RESIDENCY?
AARVI RESIDENCY by DHARMPAL OMKARMAL CHOUDHARY is in Rees, Raigarh (pincode 410222), near Khalapur, Mohopada, Maharashtra, and is registered on MahaRERA as P52000079262, per GharKundli's check of MahaRERA records.
How many homes are in AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY has 24 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was AARVI RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AARVI RESIDENCY was registered on MahaRERA on 25 February 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on AARVI RESIDENCY?
No court cases are listed for AARVI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AARVI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHARMPAL OMKARMAL CHOUDHARY.
Check it yourself on MahaRERA
- How to check the possession date of AARVI RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Rees
All 36 projects in Mohopada (410222) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.