by Capital Builders · Pushpak Node, Raigarh

Registered on MahaRERA under P52000052875, and currently active. Its completion date has moved from November 2026 to March 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Ambers Dnyaneshwar Capital

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000052875
Status
Registered and active
Builder
Capital Builders
Location
Pushpak Node, Raigarh · 410206
Project type
Others
Registered on
5 Oct 2023
Completion date at registration
November 2026
Latest completion date
March 2027
Delay so far
4 months
Homes
45
Sold or booked
34%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Ambers Dnyaneshwar Capital: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Ambers Dnyaneshwar Capital

Is Ambers Dnyaneshwar Capital registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambers Dnyaneshwar Capital is registered as P52000052875 and its status is "Registered and active".

Where is Ambers Dnyaneshwar Capital?

Ambers Dnyaneshwar Capital by Capital Builders is in Pushpak Node, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000052875, per GharKundli's check of MahaRERA records.

When is possession of Ambers Dnyaneshwar Capital due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ambers Dnyaneshwar Capital in Pushpak Node, Raigarh is 30 March 2027 — 4 months later than 30 November 2026, the date given at registration.

Does Ambers Dnyaneshwar Capital have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Ambers Dnyaneshwar Capital?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Capital Builders.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.