Skip to content
GharKundli

SHREEPATI REGALIA

by SHREEPATI GROUP · Pushpak Node, Raigarh

Registered on MahaRERA under P52000056403, and currently active. Its completion date has moved from December 2026 to April 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SHREEPATI REGALIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000056403
Status
Registered and active
Builder
SHREEPATI GROUP
Location
Pushpak Node, Raigarh · 410206
Project type
Mixed
Registered on
31 May 2024
Completion date at registration
December 2026
Latest completion date
April 2027
Delay so far
4 months
Homes
69
Sold or booked
90%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

SHREEPATI REGALIA: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SHREEPATI REGALIA

Is SHREEPATI REGALIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI REGALIA is registered as P52000056403 and its status is "Registered and active".

Where is SHREEPATI REGALIA?

SHREEPATI REGALIA by SHREEPATI GROUP is in Pushpak Node, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000056403, per GharKundli's check of MahaRERA records.

When is possession of SHREEPATI REGALIA due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREEPATI REGALIA in Pushpak Node, Raigarh is 30 April 2027 — 4 months later than 31 December 2026, the date given at registration.

Does SHREEPATI REGALIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SHREEPATI REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREEPATI GROUP, which has 1 other project registered on MahaRERA.

Other projects in pincode 410206

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.