Neelkanth Elite
by NEELKANTH PROPERTIES & DEVELOPERS · Karanjade, Raigarh
Registered on MahaRERA under PR1270002600392, and currently active. Its completion date has moved from March 2030 to July 2030, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Neelkanth Elite
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1270002600392
- Status
- Registered and active
- Builder
- NEELKANTH PROPERTIES & DEVELOPERS
- Location
- Karanjade, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 11 May 2026
- Completion date at registration
- March 2030
- Latest completion date
- July 2030
- Delay so far
- 4 months
- Homes
- 82
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
Neelkanth Elite: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Neelkanth Elite
Is Neelkanth Elite registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelkanth Elite is registered as PR1270002600392 and its status is "Registered and active".
Where is Neelkanth Elite?
Neelkanth Elite by NEELKANTH PROPERTIES & DEVELOPERS is in Karanjade, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as PR1270002600392, per GharKundli's check of MahaRERA records.
When is possession of Neelkanth Elite due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neelkanth Elite in Karanjade, Raigarh is 31 July 2030 — 4 months later than 31 March 2030, the date given at registration.
Does Neelkanth Elite have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Neelkanth Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEELKANTH PROPERTIES & DEVELOPERS, which has 1 other project registered on MahaRERA.
Other projects in pincode 410206
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.