SkyHigh Towers - D1D2

by New World Landmark LLP · Hinjewadi, Pune

Registered on MahaRERA under P52100015918, and currently active. Its completion date has moved from December 2023 to July 2028, 55 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SkyHigh Towers - D1D2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100015918
Status
Registered and active
Builder
New World Landmark LLP
Location
Hinjewadi, Pune · 411057
Project type
Residential / Group Housing
Registered on
9 Apr 2018
Completion date at registration
December 2023
Latest completion date
July 2028
Delay so far
55 months
Homes
272
Sold or booked
69%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Kundli Watch

SkyHigh Towers - D1D2: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SkyHigh Towers - D1D2

Is SkyHigh Towers - D1D2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SkyHigh Towers - D1D2 is registered as P52100015918 and its status is "Registered and active".

Where is SkyHigh Towers - D1D2?

SkyHigh Towers - D1D2 by New World Landmark LLP is in Hinjewadi, Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100015918, per GharKundli's check of MahaRERA records.

When is possession of SkyHigh Towers - D1D2 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SkyHigh Towers - D1D2 in Hinjewadi, Pune is 31 July 2028 — 55 months later than 31 December 2023, the date given at registration.

Does SkyHigh Towers - D1D2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SkyHigh Towers - D1D2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is New World Landmark LLP, which has 3 other projects registered on MahaRERA.

Other projects in pincode 411057

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.