Siyaram Sky World
by SIYARAM DEVELOPERS · Wakad, Pune 411057Also near Infotech Park (Hinjawadi)Registered on MahaRERA as “SKY WORLD”
What’s in the report? →Possession date of Siyaram Sky World (MahaRERA P52100052484): 31 October 2027, moved from 18 October 2026 (12 months later). It has 115 homes, 41% sold or booked. 1 complaint on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100052484, and currently active.
Source: MahaRERA website — records for P52100052484, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Siyaram Sky World?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Siyaram Sky World has moved
18 October 2026
Completion date given when the project was registered
18 February 2027
Extended at the builder's request
31 October 2027
Extended at the builder's request (MahaRERA application EA30092639020)
Reason the builder gave MahaRERA:
“The project has substantially progressed in accordance with the sanctioned plans. However, completion of the project within the original registration period was not possible due to delays in obtaining the Revised Sanction Plan and the conse…” Read the full reason
“The project has substantially progressed in accordance with the sanctioned plans. However, completion of the project within the original registration period was not possible due to delays in obtaining the Revised Sanction Plan and the consequential statutory approvals, which were beyond the control of the Promoter. 1. Delay in Approval of Revised Sanction Plan The revised building proposal remained pending before the Competent Planning Authority for a considerable period. As the execution of the balance construction activities was dependent upon the revised sanction, the project completion…”
Source: Siyaram Sky World’s extension records on MahaRERA (P52100052484), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Siyaram Sky World
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100052484
- Status
- Registered and active
- Builder
- SIYARAM DEVELOPERS
- Location
- Wakad, Pune · 411057
- Project type
- Residential / Group Housing
- Registered on
- 8 Sep 2023
- Completion date at registration
- October 2026
- Latest completion date
- October 2027
- Delay so far
- 12 months
- Homes
- 115
- Sold or booked
- 41%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Siyaram Sky World, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C | 100% | 100% | 90% | 70% |
| D | 100% | 100% | 90% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- C: covers 15 floors
- D: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siyaram Sky World every 1–2 months.
Siyaram Sky World: buildings, flats and land, as filed on MahaRERA
- Buildings: C (16 floors, 56 units) · D (16 floors, 59 units)
- Land: 6,400 sq m (about 1.6 acres) · sanctioned built-up 10,588 sq m · recreational space 602 sq m
- Land, as filed: S.NO. 196/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Siyaram Sky World →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Siyaram Sky World: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Siyaram Sky World
What is the possession date of Siyaram Sky World?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siyaram Sky World in Wakad, Pune is 31 October 2027 — 12 months later than 18 October 2026, the date given at registration.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Siyaram Sky World?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Siyaram Sky World's builder has filed on MahaRERA, the official one, is 31 October 2027, already 12 months later than the 18 October 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Siyaram Sky World extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World's builder applied to MahaRERA to extend the completion date 2 times: to 18 February 2027; to 31 October 2027, giving the reason "The project has substantially progressed in accordance with the sanctioned plans. However, completion of the project within the original registration period was not possible due to delays in obtaining the Revised Sanction Plan and the consequential statutory approvals, which were beyond the control of the Promoter. 1. Delay in Approval of Revised Sanction Plan The revised building proposal remained pending before the Competent Planning Authority for a considerable period. As the execution of the balance construction activities was dependent upon the revised sanction, the project completion…".
What is the RERA number of Siyaram Sky World?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Siyaram Sky World in Wakad, Pune is P52100052484.
Is Siyaram Sky World registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World is registered as P52100052484 and its status is "Registered and active".
What is the current construction status of Siyaram Sky World? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Siyaram Sky World have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →
Is Siyaram Sky World safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World is registered on MahaRERA as P52100052484, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Siyaram Sky World?
Siyaram Sky World is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Siyaram Sky World?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Siyaram Sky World: gharkundli.com/tools/property-cost-calculator
Has Siyaram Sky World received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World is still under construction, with 31 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Siyaram Sky World uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Siyaram Sky World was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Siyaram Sky World's possession date changes?
The latest dates are on Siyaram Sky World's MahaRERA page (P52100052484). GharKundli's Kundli Watch sends a free WhatsApp update on Siyaram Sky World every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Siyaram Sky World have?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World has 2 buildings filed: C with 16 floors and 56 units; D with 16 floors and 59 units.
How big is the land of Siyaram Sky World?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World stands on 6,400 sq m of land (about 1.6 acres), with 10,588 sq m of sanctioned built-up area and 602 sq m of recreational open space.
What are the reviews of Siyaram Sky World?
Google Maps has reviews of Siyaram Sky World written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Siyaram Sky World?
Siyaram Sky World by SIYARAM DEVELOPERS is in Wakad, Pune, pincode 411057 (near Infotech Park (Hinjawadi)), Maharashtra, and is registered on MahaRERA as P52100052484, per GharKundli's check of MahaRERA records. Its land is filed as S.NO. 196/2. GharKundli lists all 644 MahaRERA projects in Wakad (411057).
How many flats are in Siyaram Sky World, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World has 115 homes in 2 towers registered on MahaRERA, and 41% of them are sold or booked.
When was Siyaram Sky World registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Siyaram Sky World was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.
Does Siyaram Sky World have any legal issues or court cases?
1 court case is listed for Siyaram Sky World on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Siyaram Sky World?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIYARAM DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Siyaram Sky World
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Wakad (411057)
- Treasure Troves
- Casa Imperia
- Menlo Estella
- Truspace Prima Altiora
- Westgate Business Park
- Vyomora Phase 1
- Abharan
- Signature Park Phase - I
Other projects by SIYARAM DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.