NISARG

by WAJE & HARPALE PATIL BUILDERS · Uruli Devachi, PuneAlso near Phursungi

Registered on MahaRERA under P52100026279, and currently active. Its completion date has moved from August 2024 to April 2028: 40 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on NISARG

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026279
Status
Registered and active
Builder
WAJE & HARPALE PATIL BUILDERS
Location
Uruli Devachi, Pune · 412308
Project type
Residential / Group Housing
Registered on
4 Sep 2020
Completion date at registration
August 2024
Latest completion date
April 2028
Delay so far
40 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
102
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

NISARG: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about NISARG

Is NISARG registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NISARG is registered as P52100026279 and its status is "Registered and active".

Where is NISARG?

NISARG by WAJE & HARPALE PATIL BUILDERS is in Uruli Devachi, Pune (pincode 412308), near Phursungi, Maharashtra, and is registered on MahaRERA as P52100026279, per GharKundli's check of MahaRERA records.

When is possession of NISARG due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NISARG in Uruli Devachi, Pune is 30 April 2028 — 40 months later than 7 August 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does NISARG have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of NISARG?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is WAJE & HARPALE PATIL BUILDERS.

All projects with possession due in 2028 in Pune →

Other projects in pincode 412308

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.