Chaitanya Pacific Tower

by CHAITANYA DEVELOPERS · Phursungi, Pune 412308Registered on MahaRERA as “PACIFIC TOWER”

What’s in the report? →

Possession date of Chaitanya Pacific Tower (MahaRERA P52100034823): 30 September 2027, moved from 31 March 2026 (18 months later). It has 181 homes, 73% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100034823, and currently active.

Source: MahaRERA website — records for P52100034823, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Chaitanya Pacific Tower?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Chaitanya Pacific Tower has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 30 September 2027

    Extended at the builder's request (MahaRERA application EA10032620152)

    Reason the builder gave MahaRERA: “THE PROJECT IS COMPLETED NEARLY AROUND 55% , TO COMPLETE THE REMAINING CONSTRUCTION OF SAID PROJECT WE NEEED EXTENSION TILL DATE 30/09/2027”

Source: Chaitanya Pacific Tower’s extension records on MahaRERA (P52100034823), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Chaitanya Pacific Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100034823
Status
Registered and active
Builder
CHAITANYA DEVELOPERS
Location
Phursungi, Pune · 412308
Project type
Others
Registered on
28 Apr 2022
Completion date at registration
March 2026
Latest completion date
September 2027
Delay so far
18 months
Homes
181
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
15

Construction progress of Chaitanya Pacific Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PACIFIC TOWER100%75%75%0%

Commencement certificate (CC), as filed on MahaRERA

  • PACIFIC TOWER: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chaitanya Pacific Tower every 1–2 months.

Chaitanya Pacific Tower: buildings, flats and land, as filed on MahaRERA

  • Buildings: PACIFIC TOWER (14 floors, 193 units)
  • Car parking: 100 covered
  • Land: 6,900 sq m (about 1.7 acres) · sanctioned built-up 11,930 sq m · recreational space 692 sq m
  • Land, as filed: SURVEY NO 176 HISSA NO 7/3 AND 7/4
  • Map: Get directions

The builder’s record and reviews

SAI Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 25 months late). No complaints on MahaRERA.

Read Google reviews of Chaitanya Pacific Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Chaitanya Pacific Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Chaitanya Pacific Tower

What is the possession date of Chaitanya Pacific Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Chaitanya Pacific Tower in Phursungi, Pune is 30 September 2027 — 18 months later than 31 March 2026, the date given at registration.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Chaitanya Pacific Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Chaitanya Pacific Tower's builder has filed on MahaRERA, the official one, is 30 September 2027, already 18 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Chaitanya Pacific Tower extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "THE PROJECT IS COMPLETED NEARLY AROUND 55% , TO COMPLETE THE REMAINING CONSTRUCTION OF SAID PROJECT WE NEEED EXTENSION TILL DATE 30/09/2027".

What is the RERA number of Chaitanya Pacific Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Chaitanya Pacific Tower in Phursungi, Pune is P52100034823.

Is Chaitanya Pacific Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower is registered as P52100034823 and its status is "Registered and active".

What is the current construction status of Chaitanya Pacific Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PACIFIC TOWER is 75% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does Chaitanya Pacific Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Chaitanya Pacific Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower is registered on MahaRERA as P52100034823, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Chaitanya Pacific Tower?

Chaitanya Pacific Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Chaitanya Pacific Tower?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Chaitanya Pacific Tower: gharkundli.com/tools/property-cost-calculator

Has Chaitanya Pacific Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower is still under construction, with 30 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Chaitanya Pacific Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Chaitanya Pacific Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Chaitanya Pacific Tower's possession date changes?

The latest dates are on Chaitanya Pacific Tower's MahaRERA page (P52100034823). GharKundli's Kundli Watch sends a free WhatsApp update on Chaitanya Pacific Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Chaitanya Pacific Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower has one building filed: PACIFIC TOWER with 14 floors and 193 units.

How much parking does Chaitanya Pacific Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 100 covered car parking spaces for Chaitanya Pacific Tower.

How big is the land of Chaitanya Pacific Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower stands on 6,900 sq m of land (about 1.7 acres), with 11,930 sq m of sanctioned built-up area and 692 sq m of recreational open space.

What is the track record of Chaitanya Pacific Tower's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI Enterprises (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 25 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Chaitanya Pacific Tower?

Google Maps has reviews of Chaitanya Pacific Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Chaitanya Pacific Tower?

Chaitanya Pacific Tower by CHAITANYA DEVELOPERS is in Phursungi, Pune, pincode 412308, Maharashtra, and is registered on MahaRERA as P52100034823, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 176 HISSA NO 7/3 AND 7/4. GharKundli lists all 111 MahaRERA projects in Fursungi (412308).

How many flats are in Chaitanya Pacific Tower, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower has 181 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was Chaitanya Pacific Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Pacific Tower was registered on MahaRERA on 28 April 2022. GharKundli did not find a title report on the land on file there.

Does Chaitanya Pacific Tower have any legal issues or court cases?

No court cases are listed for Chaitanya Pacific Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Chaitanya Pacific Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHAITANYA DEVELOPERS, which has 15 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Fursungi (412308)

All 111 projects in Fursungi (412308) →

Other projects by CHAITANYA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.