Chaitanya Ethics Orovia
by Chaitanya Developers · Malad West, Mumbai 400064Also near Borivali West, Vile Parle East, Malad EastRegistered on MahaRERA as “Ethics Orovia”
What’s in the report? →Possession date of Chaitanya Ethics Orovia (MahaRERA PR1180002601346): 30 August 2031. It has 453 homes (1 BHK, 2 BHK and 3 BHK, 390–2165 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002601346, and currently active. Its completion date is now August 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002601346, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Chaitanya Ethics Orovia?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Chaitanya Ethics Orovia has moved
30 April 2031
Completion date given when the project was registered
30 August 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Chaitanya Ethics Orovia’s extension records on MahaRERA (PR1180002601346), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Chaitanya Ethics Orovia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002601346
- Status
- Registered and active
- Builder
- Chaitanya Developers
- Location
- Malad West, Mumbai · 400064
- Project type
- Residential / Group Housing
- Registered on
- 29 Jul 2026
- Completion date at registration
- April 2031
- Latest completion date
- August 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 453
- Sold or booked
- 0%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 15
Construction progress of Chaitanya Ethics Orovia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 / A Wing | 0% | 0% | 0% | 0% |
| Building No 1 / B Wing | 0% | 0% | 0% | 0% |
| Building No 2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1: covers Plinth
- Building No 1: covers Plinth
- Building No 2: covers Plinth
Latest CC order on MahaRERA: dated 21/05/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chaitanya Ethics Orovia every 1–2 months.
Chaitanya Ethics Orovia: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 733 – 1,283 | 173 |
| 1 BHK | 390 – 488 | 146 |
| 2 BHK | 479 – 2,127 | 131 |
| Shops | 129 – 267 | 7 |
| Office Space | 250 – 507 | 4 |
| Duplex | 2,165 | 3 |
- Buildings: Building No 1 (40 floors, 187 units) · Building No 1 (39 floors, 182 units) · Building No 2 (20 floors, 95 units)
- Car parking: 498 covered
- Land: 7,682 sq m (about 1.9 acres) · sanctioned built-up 32,138 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Ethics Infra Development (a group of 10 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 13 finished, 5 within the promised date and 8 needed more time (typically 10 months); 5 still being built, 1 past the promised date (typically 39 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Chaitanya Ethics Orovia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Chaitanya Ethics Orovia: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Chaitanya Ethics Orovia
What is the possession date of Chaitanya Ethics Orovia?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Chaitanya Ethics Orovia in Malad West, Mumbai is 30 August 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Chaitanya Ethics Orovia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Chaitanya Ethics Orovia's builder has filed on MahaRERA, the official one, is 30 August 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Chaitanya Ethics Orovia?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Chaitanya Ethics Orovia in Malad West, Mumbai is PR1180002601346.
Is Chaitanya Ethics Orovia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia is registered as PR1180002601346 and its status is "Registered and active".
What is the current construction status of Chaitanya Ethics Orovia? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Chaitanya Ethics Orovia have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Chaitanya Ethics Orovia safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia is registered on MahaRERA as PR1180002601346, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Chaitanya Ethics Orovia?
Chaitanya Ethics Orovia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Chaitanya Ethics Orovia are 390 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Chaitanya Ethics Orovia?
For a flat in Chaitanya Ethics Orovia (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Chaitanya Ethics Orovia received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia is still under construction, with 30 August 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Chaitanya Ethics Orovia a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia is a redevelopment: 159 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Chaitanya Ethics Orovia uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Chaitanya Ethics Orovia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Chaitanya Ethics Orovia's possession date changes?
The latest dates are on Chaitanya Ethics Orovia's MahaRERA page (PR1180002601346). GharKundli's Kundli Watch sends a free WhatsApp update on Chaitanya Ethics Orovia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Chaitanya Ethics Orovia have?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia has 3 buildings filed: Building No 1 with 40 floors and 187 units; Building No 1 with 39 floors and 182 units; Building No 2 with 20 floors and 95 units.
What are the flat sizes (carpet area) in Chaitanya Ethics Orovia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Chaitanya Ethics Orovia: 3 BHK: 733 to 1283 sq ft carpet (173 homes); 1 BHK: 390 to 488 sq ft carpet (146 homes); 2 BHK: 479 to 2127 sq ft carpet (131 homes); Duplex: 2165 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Chaitanya Ethics Orovia have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 498 covered car parking spaces for Chaitanya Ethics Orovia.
How big is the land of Chaitanya Ethics Orovia?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia stands on 7,682 sq m of land (about 1.9 acres), with 32,138 sq m of sanctioned built-up area.
What is the track record of Chaitanya Ethics Orovia's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ethics Infra Development (a group of 10 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 13 finished, 5 within the promised date and 8 needed more time (typically 10 months); 5 still being built, 1 past the promised date (typically 39 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Chaitanya Ethics Orovia?
Google Maps has reviews of Chaitanya Ethics Orovia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Chaitanya Ethics Orovia?
Chaitanya Ethics Orovia by Chaitanya Developers is in Malad West, Mumbai, pincode 400064 (near Borivali West, Vile Parle East, Malad East), Maharashtra, and is registered on MahaRERA as PR1180002601346, per GharKundli's check of MahaRERA records. GharKundli lists all 301 MahaRERA projects in Malad West (400064).
How many flats are in Chaitanya Ethics Orovia, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia has 453 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Chaitanya Ethics Orovia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chaitanya Ethics Orovia was registered on MahaRERA on 29 July 2026. GharKundli did not find a title report on the land on file there.
Does Chaitanya Ethics Orovia have any legal issues or court cases?
No court cases are listed for Chaitanya Ethics Orovia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Chaitanya Ethics Orovia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Chaitanya Developers, which has 15 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Chaitanya Ethics Orovia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Mumbai Suburban →
Other projects in Malad West (400064)
- Florence Residency
- Aabiel Avenue
- Rashmi Icon
- Maru Mansion
- Rite Amor
- Avirahi Elegance
- Bhagat Grandeur
- Lotus Sky Garden
Other projects by Chaitanya Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.