Bhagat Grandeur
by Chirag Agro Fins Private Limited · Borivali, MumbaiAlso near Malad West, Vile Parle East, Worli
Possession date of Bhagat Grandeur: 29 April 2027, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800009520, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Bhagat Grandeur?
How the possession date of Bhagat Grandeur has moved
31 December 2018
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT51800001909)
Reason the builder gave MahaRERA:
“We have obtained Part Occupation Certificate upto 17th Floor, which has already been uploaded on the webpage of our said Project on official website of MahaRERA. The Occupation Certificate of 18th and 19th Floors is pending, which has alrea…” Read the full reason
“We have obtained Part Occupation Certificate upto 17th Floor, which has already been uploaded on the webpage of our said Project on official website of MahaRERA. The Occupation Certificate of 18th and 19th Floors is pending, which has already been communicated to the Allottee / Purchaser of the said Project. We assure you that rights and interest of the Allottees / Purchaser in the Project shall not affect due to amendment of layout plan for mandatory reservation and we shall arrange to obtain the consent of Allottee, wherever necessary, to complete the statutory process. We are committed t…”31 December 2020
Extended at the builder's request (MahaRERA application EXT51800005860)
Reason the builder gave MahaRERA:
“Due to the effect of notified DCPR, 2034, there is proposed amendment regarding mandatory reservation of ' police station/ Bit Chawki on the plot under the layout of project land, for which shifting/relocationf of the said reservation neede…” Read the full reason
“Due to the effect of notified DCPR, 2034, there is proposed amendment regarding mandatory reservation of ' police station/ Bit Chawki on the plot under the layout of project land, for which shifting/relocationf of the said reservation needed approval from competent authorities of MCGM. Without completing such process full ocupation of the project may not be issued by the competent authority of MCGM. Consequantely the project extention date under RERA needs to be extended for once again under the provisions of MahaRERA.”30 June 2022
Extended at the builder's request (MahaRERA application EXT51800011205)
Reason the builder gave MahaRERA:
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availabilit…” Read the full reason
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending.”30 December 2023
Extended at the builder's request (MahaRERA application EXT51800012487)
Reason the builder gave MahaRERA:
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availabilit…” Read the full reason
“1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending.”29 December 2026
Extended at the builder's request (MahaRERA application EXT51800018954)
Reason the builder gave MahaRERA:
“The project is already completed and received OC for 1st to 16th floor. But OC is not given for 17th and 18th floor and getting delayed due to technical reason i.e. MCGM objection on police station reservation on the broader area of various…” Read the full reason
“The project is already completed and received OC for 1st to 16th floor. But OC is not given for 17th and 18th floor and getting delayed due to technical reason i.e. MCGM objection on police station reservation on the broader area of various plots in which our plot is also situated.”29 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Bhagat Grandeur’s extension records on MahaRERA (P51800009520), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhagat Grandeur
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009520
- Status
- Registered and active
- Builder
- Chirag Agro Fins Private Limited
- Location
- Borivali, Mumbai · 400064
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- April 2027
- Delay so far
- 96 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 90
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Bhagat Grandeur, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bhagat Grandeur | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Bhagat Grandeur: covers 18 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhagat Grandeur every month.
Bhagat Grandeur: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 771 – 773 | 50 |
| 3 BHK | 1,078 | 26 |
| Shops | 814 – 3,238 | 8 |
| Duplex | 1,474 – 1,543 | 6 |
- Buildings: Bhagat Grandeur (24 floors, 90 units)
- Car parking: 223 covered, 7 open
- Land: 4,146 sq m (about 1.0 acres) · sanctioned built-up 10,425 sq m · recreational space 829 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bhagat Grandeur →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhagat Grandeur: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bhagat Grandeur
What is the possession date of Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhagat Grandeur in Borivali, Mumbai is 29 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Bhagat Grandeur?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhagat Grandeur's builder has filed on MahaRERA, the official one, is 29 April 2027, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhagat Grandeur extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur's builder applied to MahaRERA to extend the completion date 5 times: to 31 December 2020, giving the reason "We have obtained Part Occupation Certificate upto 17th Floor, which has already been uploaded on the webpage of our said Project on official website of MahaRERA. The Occupation Certificate of 18th and 19th Floors is pending, which has already been communicated to the Allottee / Purchaser of the said Project. We assure you that rights and interest of the Allottees / Purchaser in the Project shall not affect due to amendment of layout plan for mandatory reservation and we shall arrange to obtain the consent of Allottee, wherever necessary, to complete the statutory process. We are committed t…"; to 31 December 2020, giving the reason "Due to the effect of notified DCPR, 2034, there is proposed amendment regarding mandatory reservation of ' police station/ Bit Chawki on the plot under the layout of project land, for which shifting/relocationf of the said reservation needed approval from competent authorities of MCGM. Without completing such process full ocupation of the project may not be issued by the competent authority of MCGM. Consequantely the project extention date under RERA needs to be extended for once again under the provisions of MahaRERA."; to 30 June 2022, giving the reason "1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending."; to 30 December 2023, giving the reason "1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending."; to 29 December 2026, giving the reason "The project is already completed and received OC for 1st to 16th floor. But OC is not given for 17th and 18th floor and getting delayed due to technical reason i.e. MCGM objection on police station reservation on the broader area of various plots in which our plot is also situated.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhagat Grandeur in Borivali, Mumbai is P51800009520.
Is Bhagat Grandeur registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur is registered as P51800009520 and its status is "Registered and active".
What is the construction status of Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Bhagat Grandeur is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Bhagat Grandeur have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bhagat Grandeur safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur is registered on MahaRERA as P51800009520, its completion date has moved 96 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bhagat Grandeur's possession date changes?
The latest dates are on Bhagat Grandeur's MahaRERA page (P51800009520). GharKundli's Kundli Watch sends a free WhatsApp update on Bhagat Grandeur every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhagat Grandeur have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur has one building filed: Bhagat Grandeur with 24 floors and 90 units.
What are the flat sizes (carpet area) in Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bhagat Grandeur: 2 BHK: 771 to 773 sq ft carpet (50 homes); 3 BHK: 1078 sq ft carpet (26 homes); Shops: 814 to 3238 sq ft carpet (8 homes); Duplex: 1474 to 1543 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Bhagat Grandeur have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 223 covered and 7 open car parking spaces for Bhagat Grandeur.
How big is the land of Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur stands on 4,146 sq m of land (about 1.0 acres), with 10,425 sq m of sanctioned built-up area and 829 sq m of recreational open space.
Where can I read reviews of Bhagat Grandeur?
Google Maps has reviews of Bhagat Grandeur written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bhagat Grandeur?
Bhagat Grandeur by Chirag Agro Fins Private Limited is in Borivali, Mumbai (pincode 400064), near Malad West, Vile Parle East, Worli, Maharashtra, and is registered on MahaRERA as P51800009520, per GharKundli's check of MahaRERA records.
How many homes are in Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur has 90 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was Bhagat Grandeur registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhagat Grandeur was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bhagat Grandeur?
No court cases are listed for Bhagat Grandeur on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Bhagat Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Chirag Agro Fins Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Bhagat Grandeur
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- SCORPIO
- Giriraj Gold
- SBI RAGVIHAR CHS
- Mahavir Krupa CHSL Ltd
- Ruparel Optima Ph I
- ORCHID TOWER
- PRIME AURA
- SANGHVI JEWEL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.