Possession date of SANGHVI JEWEL: 30 April 2027, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010958, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SANGHVI JEWEL?
How the possession date of SANGHVI JEWEL has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT51800000914)
Reason the builder gave MahaRERA: “we are proposing amendment in plan due to modification in Mumbai Development Rules (DCPR 2034), hence for the purpose of obtaining approval and to commence work we require further time extension.”
31 March 2024
Extended at the builder's request (MahaRERA application EXT51800010955)
Reason the builder gave MahaRERA:
“The Developer has got additional FSI due to road width provision as per Development Control Regulations and accordingly the developer has got additional FSI for constructing 8th 9th and 10th Floor of the building as per iod approval due to…” Read the full reason
“The Developer has got additional FSI due to road width provision as per Development Control Regulations and accordingly the developer has got additional FSI for constructing 8th 9th and 10th Floor of the building as per iod approval due to all this project is delayed”30 September 2025
Extended at the builder's request (MahaRERA application EXT51800025317)
Reason the builder gave MahaRERA:
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, cau…” Read the full reason
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-09-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera.”31 December 2026
Extended at the builder's request (MahaRERA application EA13102518096)
Reason the builder gave MahaRERA:
“a. Outbreak of Covid – 19 : The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and di…” Read the full reason
“a. Outbreak of Covid – 19 : The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. b. The cost of balance work to complete the construction is Rs. 3,18,10,822 which can be easily met out of receivable from ongoing project of Rs. 17,45,27,9…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SANGHVI JEWEL’s extension records on MahaRERA (P51800010958), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SANGHVI JEWEL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010958
- Status
- Registered and active
- Builder
- SANGHVI REALTORS
- Location
- Borivali, Mumbai · 400064
- Project type
- Commercial
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- April 2027
- Delay so far
- 96 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 54%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SANGHVI JEWEL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SANGHVI JEWEL BUILDING NO 1 | 100% | 80% | 60% | 60% |
| SANGHVI JEWEL BUILDING NO 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SANGHVI JEWEL BUILDING NO 1: covers 10 floors
- SANGHVI JEWEL BUILDING NO 2: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANGHVI JEWEL every month.
SANGHVI JEWEL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 168 – 904 | 37 |
- Buildings: SANGHVI JEWEL BUILDING NO 1 (11 floors, 29 units) · SANGHVI JEWEL BUILDING NO 2 (2 floors, 8 units)
- Land: 2,080 sq m (about 0.5 acres) · sanctioned built-up 3,933 sq m · recreational space 256 sq m
- Boundaries filed include: UNDERIA ROAD, KISAN ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SANGHVI JEWEL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SANGHVI JEWEL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SANGHVI JEWEL
What is the possession date of SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SANGHVI JEWEL in Borivali, Mumbai is 30 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SANGHVI JEWEL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SANGHVI JEWEL's builder has filed on MahaRERA, the official one, is 30 April 2027, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SANGHVI JEWEL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2019, giving the reason "we are proposing amendment in plan due to modification in Mumbai Development Rules (DCPR 2034), hence for the purpose of obtaining approval and to commence work we require further time extension."; to 31 March 2024, giving the reason "The Developer has got additional FSI due to road width provision as per Development Control Regulations and accordingly the developer has got additional FSI for constructing 8th 9th and 10th Floor of the building as per iod approval due to all this project is delayed"; to 30 September 2025, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-09-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera."; to 31 December 2026, giving the reason "a. Outbreak of Covid – 19 : The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. b. The cost of balance work to complete the construction is Rs. 3,18,10,822 which can be easily met out of receivable from ongoing project of Rs. 17,45,27,9…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SANGHVI JEWEL in Borivali, Mumbai is P51800010958.
Is SANGHVI JEWEL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL is registered as P51800010958 and its status is "Registered and active".
What is the construction status of SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 80% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SANGHVI JEWEL have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SANGHVI JEWEL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL is registered on MahaRERA as P51800010958, its completion date has moved 96 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SANGHVI JEWEL's possession date changes?
The latest dates are on SANGHVI JEWEL's MahaRERA page (P51800010958). GharKundli's Kundli Watch sends a free WhatsApp update on SANGHVI JEWEL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SANGHVI JEWEL have?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL has 2 buildings filed: SANGHVI JEWEL BUILDING NO 1 with 11 floors and 29 units; SANGHVI JEWEL BUILDING NO 2 with 2 floors and 8 units.
How big is the land of SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL stands on 2,080 sq m of land (about 0.5 acres), with 3,933 sq m of sanctioned built-up area and 256 sq m of recreational open space.
Where can I read reviews of SANGHVI JEWEL?
Google Maps has reviews of SANGHVI JEWEL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SANGHVI JEWEL?
SANGHVI JEWEL by SANGHVI REALTORS is in Borivali, Mumbai (pincode 400064), near Malad West, Malad East, Andheri West, Maharashtra, and is registered on MahaRERA as P51800010958, per GharKundli's check of MahaRERA records. Its boundaries filed there include UNDERIA ROAD, KISAN ROAD.
How many homes are in SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL has 0 homes in 2 towers registered on MahaRERA, and 54% of them are sold or booked.
When was SANGHVI JEWEL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SANGHVI JEWEL was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SANGHVI JEWEL?
No court cases are listed for SANGHVI JEWEL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SANGHVI JEWEL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANGHVI REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of SANGHVI JEWEL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- Bhagat Grandeur
- SCORPIO
- Giriraj Gold
- Mahavir Krupa CHSL Ltd
- SBI RAGVIHAR CHS
- Ruparel Optima Ph I
- ORCHID TOWER
- PRIME AURA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.