SCORPIO
by JASANI REALTY PVT.LTD · Borivali, MumbaiAlso near Malvani, Malad West, Kalanagar, Kharodi
Possession date of SCORPIO: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010230, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SCORPIO?
How the possession date of SCORPIO has moved
30 December 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800013035)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 60 % allottees for purpose of extension of RERA registration period of the said project.”31 December 2026
Extended at the builder's request (MahaRERA application EA17092502617)
Reason the builder gave MahaRERA:
“We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highe…” Read the full reason
“We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SCORPIO’s extension records on MahaRERA (P51800010230), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SCORPIO
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010230
- Status
- Registered and active
- Builder
- JASANI REALTY PVT.LTD
- Location
- Borivali, Mumbai · 400095
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 126
- Sold or booked
- 31%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SCORPIO, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SCORPIO | 100% | 86.95% | 85% | 15% |
Commencement certificate (CC), as filed on MahaRERA
- SCORPIO: covers 23 floors
Latest CC order on MahaRERA: dated 28/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SCORPIO every month.
SCORPIO: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 704 – 729 | 84 |
| 3 BHK | 990 – 1,034 | 42 |
| Shops | 363 – 2,903 | 13 |
- Buildings: SCORPIO (23 floors, 139 units)
- Land: 3,260 sq m (about 0.8 acres) · sanctioned built-up 7,432 sq m
- Boundaries filed include: VILLAGE MALAD ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Jasani Realty (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.
Read Google reviews of SCORPIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SCORPIO: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SCORPIO
What is the possession date of SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SCORPIO in Borivali, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SCORPIO?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SCORPIO's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SCORPIO extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 60 % allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2026, giving the reason "We are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SCORPIO in Borivali, Mumbai is P51800010230.
Is SCORPIO registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO is registered as P51800010230 and its status is "Registered and active".
What is the construction status of SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SCORPIO is 86.95% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does SCORPIO have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SCORPIO safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO is registered on MahaRERA as P51800010230, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SCORPIO's possession date changes?
The latest dates are on SCORPIO's MahaRERA page (P51800010230). GharKundli's Kundli Watch sends a free WhatsApp update on SCORPIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SCORPIO have?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO has one building filed: SCORPIO with 23 floors and 139 units.
What are the flat sizes (carpet area) in SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SCORPIO: 2 BHK: 704 to 729 sq ft carpet (84 homes); 3 BHK: 990 to 1034 sq ft carpet (42 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO stands on 3,260 sq m of land (about 0.8 acres), with 7,432 sq m of sanctioned built-up area.
What is the track record of SCORPIO's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Jasani Realty (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SCORPIO?
Google Maps has reviews of SCORPIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SCORPIO?
SCORPIO by JASANI REALTY PVT.LTD is in Borivali, Mumbai (pincode 400095), near Malvani, Malad West, Kalanagar, Kharodi, Maharashtra, and is registered on MahaRERA as P51800010230, per GharKundli's check of MahaRERA records. Its boundaries filed there include VILLAGE MALAD ROAD.
How many homes are in SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO has 126 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.
When was SCORPIO registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SCORPIO was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SCORPIO?
4 court cases are listed for SCORPIO on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SCORPIO?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JASANI REALTY PVT.LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SCORPIO
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- Bhagat Grandeur
- Giriraj Gold
- Mahavir Krupa CHSL Ltd
- SBI RAGVIHAR CHS
- Ruparel Optima Ph I
- ORCHID TOWER
- PRIME AURA
- SANGHVI JEWEL
Other projects by JASANI REALTY PVT.LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.