ADITYA ENCLAVE

by RAKHI PANKAJ CHOPADA · Infotech Park (Hinjawadi), Pune

Registered on MahaRERA under P52100050290, and currently active. Its completion date has moved from March 2026 to July 2027, 16 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on ADITYA ENCLAVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100050290
Status
Registered and active
Builder
RAKHI PANKAJ CHOPADA
Location
Infotech Park (Hinjawadi), Pune · 411057
Project type
Others
Registered on
1 Apr 2023
Completion date at registration
March 2026
Latest completion date
July 2027
Delay so far
16 months
Homes
40
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

ADITYA ENCLAVE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about ADITYA ENCLAVE

Is ADITYA ENCLAVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ADITYA ENCLAVE is registered as P52100050290 and its status is "Registered and active".

Where is ADITYA ENCLAVE?

ADITYA ENCLAVE by RAKHI PANKAJ CHOPADA is in Infotech Park (Hinjawadi), Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100050290, per GharKundli's check of MahaRERA records.

When is possession of ADITYA ENCLAVE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ADITYA ENCLAVE in Infotech Park (Hinjawadi), Pune is 31 July 2027 — 16 months later than 31 March 2026, the date given at registration.

Does ADITYA ENCLAVE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of ADITYA ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAKHI PANKAJ CHOPADA.

Other projects in pincode 411057

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.