ANANT
by Kotibhaskar Infrastructures &Developers Pvt.Ltd. · Ex. Serviceman Colony, Pune
Registered on MahaRERA under P52100053462, and currently active. Its completion date has moved from June 2026 to April 2027, 10 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on ANANT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100053462
- Status
- Registered and active
- Builder
- Kotibhaskar Infrastructures &Developers Pvt.Ltd.
- Location
- Ex. Serviceman Colony, Pune · 411038
- Project type
- Residential / Group Housing
- Registered on
- 6 Nov 2023
- Completion date at registration
- June 2026
- Latest completion date
- April 2027
- Delay so far
- 10 months
- Homes
- 60
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 27
Kundli Watch
ANANT: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about ANANT
Is ANANT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANANT is registered as P52100053462 and its status is "Registered and active".
Where is ANANT?
ANANT by Kotibhaskar Infrastructures &Developers Pvt.Ltd. is in Ex. Serviceman Colony, Pune (pincode 411038), Maharashtra, and is registered on MahaRERA as P52100053462, per GharKundli's check of MahaRERA records.
When is possession of ANANT due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANANT in Ex. Serviceman Colony, Pune is 30 April 2027 — 10 months later than 30 June 2026, the date given at registration.
Does ANANT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of ANANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kotibhaskar Infrastructures &Developers Pvt.Ltd., which has 27 other projects registered on MahaRERA.
Other projects in pincode 411038
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.