Silver Tarika
by Chaphalkar Schemes · Modern Colony , Shivteerth Nagar, Pune 411038
What’s in the report? →Possession date of Silver Tarika (MahaRERA P52100027116): 30 April 2027, moved from 30 June 2025 (18 months later). It has 70 homes, 94% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100027116, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100027116, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Silver Tarika?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Silver Tarika has moved
30 June 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EA27092517962)
Reason the builder gave MahaRERA:
“1. Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2. However, due to procedural delays at the competent authority’s end, the Full OC is s…” Read the full reason
“1. Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2. However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3. Consequently, we are unable to complete the formalities within the stipulated RERA timeline. Therefore, we seek an extension of the project’s timeline to enable completion of the fin…”31 December 2026
Extended at the builder's request (MahaRERA application EA08072621696)
Reason the builder gave MahaRERA:
“1.Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2.However, due to procedural delays at the competent authority’s end, the Full OC is sti…” Read the full reason
“1.Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2.However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3.Consequently, we are unable to complete the formalities within the stipulated RERA timeline. Therefore, we seek an extension of the project’s timeline to enable completion of the final…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Silver Tarika’s extension records on MahaRERA (P52100027116), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Silver Tarika
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100027116
- Status
- Registered and active
- Builder
- Chaphalkar Schemes
- Location
- Modern Colony , Shivteerth Nagar, Pune · 411038
- Project type
- Residential / Group Housing
- Registered on
- 19 Nov 2020
- Completion date at registration
- June 2025
- Latest completion date
- April 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 70
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Silver Tarika, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Silver Tarika | 100% | 100% | 100% | 98% |
Commencement certificate (CC), as filed on MahaRERA
- Silver Tarika: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Silver Tarika every 1–2 months.
Silver Tarika: buildings, flats and land, as filed on MahaRERA
- Buildings: Silver Tarika (9 floors, 70 units)
- Land: 1,943 sq m (about 0.5 acres) · sanctioned built-up 6,714 sq m
- Land, as filed: Plot no.40, 21 Part, CTS no.924 and 925 part , S.No.120
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Silver Tarika →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Silver Tarika: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Silver Tarika
What is the possession date of Silver Tarika?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Silver Tarika in Modern Colony , Shivteerth Nagar, Pune is 30 April 2027 — 18 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Silver Tarika?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Silver Tarika's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Silver Tarika extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "1. Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2. However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3. Consequently, we are unable to complete the formalities within the stipulated RERA timeline. Therefore, we seek an extension of the project’s timeline to enable completion of the fin…"; to 31 December 2026, giving the reason "1.Our project Silver Tarika has been physically completed in all respects, which is duly supported by the latest uploaded Form–1 Architect Certificate. 2.However, due to procedural delays at the competent authority’s end, the Full OC is still pending. We have submitted all requisite documents and compliances within the prescribed timelines, but the clearance process is yet to be finalized by the authority. 3.Consequently, we are unable to complete the formalities within the stipulated RERA timeline. Therefore, we seek an extension of the project’s timeline to enable completion of the final…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Silver Tarika?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Silver Tarika in Modern Colony , Shivteerth Nagar, Pune is P52100027116.
Is Silver Tarika registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika is registered as P52100027116 and its status is "Registered and active".
What is the current construction status of Silver Tarika? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Silver Tarika is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Silver Tarika have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Silver Tarika safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika is registered on MahaRERA as P52100027116, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Silver Tarika?
Silver Tarika is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Silver Tarika?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Silver Tarika: gharkundli.com/tools/property-cost-calculator
Has Silver Tarika received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Silver Tarika a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika is a redevelopment: 36 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Silver Tarika uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Silver Tarika was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Silver Tarika's possession date changes?
The latest dates are on Silver Tarika's MahaRERA page (P52100027116). GharKundli's Kundli Watch sends a free WhatsApp update on Silver Tarika every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Silver Tarika have?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika has one building filed: Silver Tarika with 9 floors and 70 units.
How big is the land of Silver Tarika?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika stands on 1,943 sq m of land (about 0.5 acres), with 6,714 sq m of sanctioned built-up area.
What are the reviews of Silver Tarika?
Google Maps has reviews of Silver Tarika written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Silver Tarika?
Silver Tarika by Chaphalkar Schemes is in Modern Colony , Shivteerth Nagar, Pune, pincode 411038, Maharashtra, and is registered on MahaRERA as P52100027116, per GharKundli's check of MahaRERA records. Its land is filed as Plot no.40, 21 Part, CTS no.924 and 925 part , S.No.120. GharKundli lists all 428 MahaRERA projects in Kothrud (411038).
How many flats are in Silver Tarika, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika has 70 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was Silver Tarika registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Tarika was registered on MahaRERA on 19 November 2020. GharKundli did not find a title report on the land on file there.
Does Silver Tarika have any legal issues or court cases?
No court cases are listed for Silver Tarika on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Silver Tarika?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Chaphalkar Schemes.
Check it yourself on MahaRERA
- How to check the possession date of Silver Tarika
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Haveli
- Madhughat
- Kesar Kalhaar
- SnehKunj
- Adi Prime
- Balwant Empire
- Cullinan
- Siddhi Aurum
- Dynamic Solitaire – Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.