CASALINO TOWERS PHASE 3

by Sai Siddhi Promoters & Builders · Outade Handewadi, Pune

Registered on MahaRERA under P52100055278, and currently active. Its completion date has moved from October 2026 to February 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on CASALINO TOWERS PHASE 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100055278
Status
Registered and active
Builder
Sai Siddhi Promoters & Builders
Location
Outade Handewadi, Pune · 412308
Project type
Residential / Group Housing
Registered on
14 Mar 2024
Completion date at registration
October 2026
Latest completion date
February 2027
Delay so far
4 months
Homes
122
Sold or booked
34%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

CASALINO TOWERS PHASE 3: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about CASALINO TOWERS PHASE 3

Is CASALINO TOWERS PHASE 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CASALINO TOWERS PHASE 3 is registered as P52100055278 and its status is "Registered and active".

Where is CASALINO TOWERS PHASE 3?

CASALINO TOWERS PHASE 3 by Sai Siddhi Promoters & Builders is in Outade Handewadi, Pune (pincode 412308), Maharashtra, and is registered on MahaRERA as P52100055278, per GharKundli's check of MahaRERA records.

When is possession of CASALINO TOWERS PHASE 3 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CASALINO TOWERS PHASE 3 in Outade Handewadi, Pune is 1 February 2027 — 4 months later than 1 October 2026, the date given at registration.

Does CASALINO TOWERS PHASE 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of CASALINO TOWERS PHASE 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sai Siddhi Promoters & Builders.

Other projects in pincode 412308

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.

CASALINO TOWERS PHASE 3, Outade Handewadi, Pune: MahaRERA status, possession & complaints