PARASNATH TOWNSHIP
by SHREENATH ENTERPRISES · Panchali Gram Panchayat, Palghar
Registered on MahaRERA under P99000015590, and currently active. Its completion date has moved from March 2020 to July 2028, 100 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on PARASNATH TOWNSHIP
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000015590
- Status
- Registered and active
- Builder
- SHREENATH ENTERPRISES
- Location
- Panchali Gram Panchayat, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 8 Mar 2018
- Completion date at registration
- March 2020
- Latest completion date
- July 2028
- Delay so far
- 100 months
- Homes
- 130
- Sold or booked
- 70%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Kundli Watch
PARASNATH TOWNSHIP: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about PARASNATH TOWNSHIP
Is PARASNATH TOWNSHIP registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PARASNATH TOWNSHIP is registered as P99000015590 and its status is "Registered and active".
Where is PARASNATH TOWNSHIP?
PARASNATH TOWNSHIP by SHREENATH ENTERPRISES is in Panchali Gram Panchayat, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000015590, per GharKundli's check of MahaRERA records.
When is possession of PARASNATH TOWNSHIP due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARASNATH TOWNSHIP in Panchali Gram Panchayat, Palghar is 31 July 2028 — 100 months later than 31 March 2020, the date given at registration.
Does PARASNATH TOWNSHIP have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of PARASNATH TOWNSHIP?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREENATH ENTERPRISES, which has 11 other projects registered on MahaRERA.
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.