The Heaven-1
by OM GAYATRI BUILDER AND DEVELOPER · Kondhan, Palghar
Registered on MahaRERA under P99000016724, and currently active. Its completion date has moved from May 2023 to July 2028: 58 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on The Heaven-1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000016724
- Status
- Registered and active
- Builder
- OM GAYATRI BUILDER AND DEVELOPER
- Location
- Kondhan, Palghar · 401404
- Project type
- Mixed
- Registered on
- 5 Jun 2018
- Completion date at registration
- May 2023
- Latest completion date
- July 2028
- Delay so far
- 58 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Towers
- 52
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
The Heaven-1: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about The Heaven-1
Is The Heaven-1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Heaven-1 is registered as P99000016724 and its status is "Registered and active".
Where is The Heaven-1?
The Heaven-1 by OM GAYATRI BUILDER AND DEVELOPER is in Kondhan, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000016724, per GharKundli's check of MahaRERA records.
When is possession of The Heaven-1 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Heaven-1 in Kondhan, Palghar is 31 July 2028 — 58 months later than 30 May 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does The Heaven-1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of The Heaven-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OM GAYATRI BUILDER AND DEVELOPER, which has 1 other project registered on MahaRERA.
All projects with possession due in 2028 in Palghar →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.