GREEN PARK
by M/S SAI SIDDHI DEVELOPERS · Palghar, Palghar
Registered on MahaRERA under P99000017023, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on GREEN PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000017023
- Status
- Registered and active
- Builder
- M/S SAI SIDDHI DEVELOPERS
- Location
- Palghar, Palghar · 401404
- Project type
- Others
- Registered on
- 4 Jul 2018
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 80
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
GREEN PARK: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about GREEN PARK
Is GREEN PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN PARK is registered as P99000017023 and its status is "Registered and active".
Where is GREEN PARK?
GREEN PARK by M/S SAI SIDDHI DEVELOPERS is in Palghar, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000017023, per GharKundli's check of MahaRERA records.
When is possession of GREEN PARK due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GREEN PARK in Palghar, Palghar is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does GREEN PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of GREEN PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S SAI SIDDHI DEVELOPERS.
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.