MAJESTIQUE MARBELLA PHASE III
by Majestique Empire LLP · Kharadi Pune, Pune
Registered on MahaRERA under P52100030934. Status: Completed. Its completion date has moved from December 2024 to September 2025, 9 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on MAJESTIQUE MARBELLA PHASE III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100030934
- Status
- Completed
- Builder
- Majestique Empire LLP
- Location
- Kharadi Pune, Pune · 411014
- Project type
- Commercial
- Registered on
- 29 Sep 2021
- Completion date at registration
- December 2024
- Latest completion date
- September 2025
- Delay so far
- 9 months
- Homes
- 0
- Sold or booked
- 91%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Kundli Watch
MAJESTIQUE MARBELLA PHASE III: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about MAJESTIQUE MARBELLA PHASE III
Is MAJESTIQUE MARBELLA PHASE III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MAJESTIQUE MARBELLA PHASE III is registered as P52100030934 and its status is "Completed".
Where is MAJESTIQUE MARBELLA PHASE III?
MAJESTIQUE MARBELLA PHASE III by Majestique Empire LLP is in Kharadi Pune, Pune (pincode 411014), Maharashtra, and is registered on MahaRERA as P52100030934, per GharKundli's check of MahaRERA records.
When is possession of MAJESTIQUE MARBELLA PHASE III due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAJESTIQUE MARBELLA PHASE III in Kharadi Pune, Pune is 30 September 2025 — 9 months later than 31 December 2024, the date given at registration.
Does MAJESTIQUE MARBELLA PHASE III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of MAJESTIQUE MARBELLA PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Majestique Empire LLP, which has 5 other projects registered on MahaRERA.
Other projects in pincode 411014
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.