Nyati Evoque
by NYATI BUILDERS PRIVATE LIMITED · Dunkirk lines, Pune 411014Also near Vadgaonsheri, Vadgaon Sheri, Sangamwadi
What’s in the report? →Possession date of Nyati Evoque (MahaRERA P52100056152): 30 April 2028. It has 196 homes, 25% sold or booked. 1 complaint on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100056152, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P52100056152, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Nyati Evoque?
1 complaint MahaRERA par. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nyati Evoque has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Nyati Evoque’s extension records on MahaRERA (P52100056152), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nyati Evoque
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100056152
- Status
- Registered and active
- Builder
- NYATI BUILDERS PRIVATE LIMITED
- Location
- Dunkirk lines, Pune · 411014
- Project type
- Others
- Registered on
- 16 May 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 196
- Sold or booked
- 25%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of Nyati Evoque, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING-A1 | 95% | 73% | 17.47% | 3.17% |
| WING-A2 | 95% | 70% | 10.92% | 2.56% |
| WING-B ANCHOR SHOP | 90% | 70% | 9.94% | 0.48% |
Commencement certificate (CC), as filed on MahaRERA
- WING-A1: covers 29 floors
- WING-A2: covers 24 floors
- WING-B ANCHOR SHOP: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nyati Evoque every 1–2 months.
Nyati Evoque: buildings, flats and land, as filed on MahaRERA
- Buildings: WING-A1 (29 floors, 116 units) · WING-A2 (24 floors, 98 units) · WING-B ANCHOR SHOP (3 floors, 3 units)
- Land: 7,362 sq m (about 1.8 acres) · sanctioned built-up 37,735 sq m · recreational space 736 sq m
- Land, as filed: SURVEY NO-5/3/1B/2, 8/2/10, 8/2/11, 9/1 PART, FINAL PLOT-B, VADGAONSHERI, PUNE
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nyati Evoque →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nyati Evoque: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nyati Evoque
What is the possession date of Nyati Evoque?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nyati Evoque in Dunkirk lines, Pune is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Nyati Evoque?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nyati Evoque's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Nyati Evoque?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nyati Evoque in Dunkirk lines, Pune is P52100056152.
Is Nyati Evoque registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque is registered as P52100056152 and its status is "Registered and active".
What is the current construction status of Nyati Evoque? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 70% to 73% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Nyati Evoque have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →
Is Nyati Evoque safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque is registered on MahaRERA as P52100056152, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nyati Evoque?
Nyati Evoque is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nyati Evoque?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nyati Evoque: gharkundli.com/tools/property-cost-calculator
Has Nyati Evoque received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Nyati Evoque uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nyati Evoque was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nyati Evoque's possession date changes?
The latest dates are on Nyati Evoque's MahaRERA page (P52100056152). GharKundli's Kundli Watch sends a free WhatsApp update on Nyati Evoque every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nyati Evoque have?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque has 3 buildings filed: WING-A1 with 29 floors and 116 units; WING-A2 with 24 floors and 98 units; WING-B ANCHOR SHOP with 3 floors and 3 units.
How big is the land of Nyati Evoque?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque stands on 7,362 sq m of land (about 1.8 acres), with 37,735 sq m of sanctioned built-up area and 736 sq m of recreational open space.
What are the reviews of Nyati Evoque?
Google Maps has reviews of Nyati Evoque written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nyati Evoque?
Nyati Evoque by NYATI BUILDERS PRIVATE LIMITED is in Dunkirk lines, Pune, pincode 411014 (near Vadgaonsheri, Vadgaon Sheri, Sangamwadi), Maharashtra, and is registered on MahaRERA as P52100056152, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO-5/3/1B/2, 8/2/10, 8/2/11, 9/1 PART, FINAL PLOT-B, VADGAONSHERI, PUNE. GharKundli lists all 323 MahaRERA projects in Kharadi (411014).
How many flats are in Nyati Evoque, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque has 196 homes in 3 towers registered on MahaRERA, and 25% of them are sold or booked.
When was Nyati Evoque registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nyati Evoque was registered on MahaRERA on 16 May 2024. GharKundli did not find a title report on the land on file there.
Does Nyati Evoque have any legal issues or court cases?
No court cases are listed for Nyati Evoque on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Nyati Evoque?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NYATI BUILDERS PRIVATE LIMITED, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nyati Evoque
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Kharadi (411014)
- Ganga Altus Kharadi Pune
- Ayodhyaa Niwaas
- Harmony Heights
- Titan Tower
- The Monarch
- Vishal Leela Residency
- Mangal Vastu
- Atulyam-Inclusive Housing
Other projects by NYATI BUILDERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.