Solitaire Business Hub - Vimannagar PH - III
by Florett Real Estate Developers Private Limited · Lohgoan South, Pune
Registered on MahaRERA under P52100080055, and currently active. Its completion date has moved from December 2030 to April 2031, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Solitaire Business Hub - Vimannagar PH - III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100080055
- Status
- Registered and active
- Builder
- Florett Real Estate Developers Private Limited
- Location
- Lohgoan South, Pune · 411014
- Project type
- Commercial
- Registered on
- 22 Apr 2025
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- Delay so far
- 4 months
- Homes
- 0
- Sold or booked
- 40%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
Solitaire Business Hub - Vimannagar PH - III: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Solitaire Business Hub - Vimannagar PH - III
Is Solitaire Business Hub - Vimannagar PH - III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub - Vimannagar PH - III is registered as P52100080055 and its status is "Registered and active".
Where is Solitaire Business Hub - Vimannagar PH - III?
Solitaire Business Hub - Vimannagar PH - III by Florett Real Estate Developers Private Limited is in Lohgoan South, Pune (pincode 411014), Maharashtra, and is registered on MahaRERA as P52100080055, per GharKundli's check of MahaRERA records.
When is possession of Solitaire Business Hub - Vimannagar PH - III due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Solitaire Business Hub - Vimannagar PH - III in Lohgoan South, Pune is 30 April 2031 — 4 months later than 31 December 2030, the date given at registration.
Does Solitaire Business Hub - Vimannagar PH - III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Solitaire Business Hub - Vimannagar PH - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Florett Real Estate Developers Private Limited.
Other projects in pincode 411014
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.