Haware Nakshatra Phase 3
by Haware Infotech Ltd · Opp Dandekar College, Palghar
Registered on MahaRERA under P99000022307, and currently active. Its completion date has moved from December 2024 to April 2027, 28 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Haware Nakshatra Phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000022307
- Status
- Registered and active
- Builder
- Haware Infotech Ltd
- Location
- Opp Dandekar College, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 9 Sep 2019
- Completion date at registration
- December 2024
- Latest completion date
- April 2027
- Delay so far
- 28 months
- Homes
- 113
- Sold or booked
- 9%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Kundli Watch
Haware Nakshatra Phase 3: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Haware Nakshatra Phase 3
Is Haware Nakshatra Phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Haware Nakshatra Phase 3 is registered as P99000022307 and its status is "Registered and active".
Where is Haware Nakshatra Phase 3?
Haware Nakshatra Phase 3 by Haware Infotech Ltd is in Opp Dandekar College, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000022307, per GharKundli's check of MahaRERA records.
When is possession of Haware Nakshatra Phase 3 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Haware Nakshatra Phase 3 in Opp Dandekar College, Palghar is 30 April 2027 — 28 months later than 30 December 2024, the date given at registration.
Does Haware Nakshatra Phase 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Haware Nakshatra Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Haware Infotech Ltd, which has 2 other projects registered on MahaRERA.
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.