Registered on MahaRERA under P99000024416, and currently active. Its completion date has moved from December 2023 to April 2029: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHREE NIWAS 8
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000024416
- Status
- Registered and active
- Builder
- PRAVIN MADHUKAR RAUT
- Location
- Saphale East, Palghar · 401102
- Project type
- Residential / Group Housing
- Registered on
- 12 Feb 2020
- Completion date at registration
- December 2023
- Latest completion date
- April 2029
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 47
- Sold or booked
- 9%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHREE NIWAS 8: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHREE NIWAS 8
Is SHREE NIWAS 8 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE NIWAS 8 is registered as P99000024416 and its status is "Registered and active".
Where is SHREE NIWAS 8?
SHREE NIWAS 8 by PRAVIN MADHUKAR RAUT is in Saphale East, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000024416, per GharKundli's check of MahaRERA records.
When is possession of SHREE NIWAS 8 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE NIWAS 8 in Saphale East, Palghar is 30 April 2029 — 60 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does SHREE NIWAS 8 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in SHREE NIWAS 8?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE NIWAS 8 has 47 homes in 1 tower registered on MahaRERA, and 9% of them are sold or booked.
When was SHREE NIWAS 8 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE NIWAS 8 was registered on MahaRERA on 12 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE NIWAS 8?
No court cases are listed for SHREE NIWAS 8 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHREE NIWAS 8?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRAVIN MADHUKAR RAUT.
All projects with possession due in 2029 in Palghar →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.