Evening Season
by ABHIJEET HAMBIRRAO KHARADE · Kudache Mala, Kolhapur
Registered on MahaRERA under P53000028885, and currently active. Its completion date has moved from June 2023 to October 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Evening Season
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000028885
- Status
- Registered and active
- Builder
- ABHIJEET HAMBIRRAO KHARADE
- Location
- Kudache Mala, Kolhapur · 416115
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2021
- Completion date at registration
- June 2023
- Latest completion date
- October 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 37
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
Evening Season: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Evening Season
Is Evening Season registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Evening Season is registered as P53000028885 and its status is "Registered and active".
Where is Evening Season?
Evening Season by ABHIJEET HAMBIRRAO KHARADE is in Kudache Mala, Kolhapur (pincode 416115), Maharashtra, and is registered on MahaRERA as P53000028885, per GharKundli's check of MahaRERA records.
When is possession of Evening Season due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Evening Season in Kudache Mala, Kolhapur is 30 October 2027 — 48 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does Evening Season have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in Evening Season?
According to GharKundli's check of MahaRERA records (updated October 2026), Evening Season has 37 homes in 1 tower registered on MahaRERA.
When was Evening Season registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Evening Season was registered on MahaRERA on 5 April 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Evening Season?
No court cases are listed for Evening Season on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Evening Season?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ABHIJEET HAMBIRRAO KHARADE.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.