SHRUSHTI RESIDENCY

by SAI VIRAJ REALTORS · Palghar West, Palghar

Registered on MahaRERA under P99000046577, and currently active. Its completion date has moved from December 2024 to December 2027, 36 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SHRUSHTI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000046577
Status
Registered and active
Builder
SAI VIRAJ REALTORS
Location
Palghar West, Palghar · 401404
Project type
Residential / Group Housing
Registered on
19 Aug 2022
Completion date at registration
December 2024
Latest completion date
December 2027
Delay so far
36 months
Homes
29
Sold or booked
34%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

SHRUSHTI RESIDENCY: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SHRUSHTI RESIDENCY

Is SHRUSHTI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRUSHTI RESIDENCY is registered as P99000046577 and its status is "Registered and active".

Where is SHRUSHTI RESIDENCY?

SHRUSHTI RESIDENCY by SAI VIRAJ REALTORS is in Palghar West, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000046577, per GharKundli's check of MahaRERA records.

When is possession of SHRUSHTI RESIDENCY due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRUSHTI RESIDENCY in Palghar West, Palghar is 31 December 2027 — 36 months later than 31 December 2024, the date given at registration.

Does SHRUSHTI RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SHRUSHTI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI VIRAJ REALTORS.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401404

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.