RAY PALMS

by SVS ELEVATE LLP · Navali Palghar West, Palghar

Registered on MahaRERA under P99000080533, and currently active. Its completion date has moved from June 2029 to October 2029, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on RAY PALMS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000080533
Status
Registered and active
Builder
SVS ELEVATE LLP
Location
Navali Palghar West, Palghar · 401404
Project type
Others
Registered on
16 Jun 2025
Completion date at registration
June 2029
Latest completion date
October 2029
Delay so far
4 months
Homes
70
Sold or booked
30%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

RAY PALMS: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about RAY PALMS

Is RAY PALMS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAY PALMS is registered as P99000080533 and its status is "Registered and active".

Where is RAY PALMS?

RAY PALMS by SVS ELEVATE LLP is in Navali Palghar West, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000080533, per GharKundli's check of MahaRERA records.

When is possession of RAY PALMS due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAY PALMS in Navali Palghar West, Palghar is 30 October 2029 — 4 months later than 30 June 2029, the date given at registration.

Does RAY PALMS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of RAY PALMS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SVS ELEVATE LLP.

Other projects in pincode 401404

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.