SHREE DAYARAM RESIDENCY 1F
by PARSHIV BUILDERS & DEVELOPERS · Palghar West, Palghar
Registered on MahaRERA under PR1240002501666, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHREE DAYARAM RESIDENCY 1F
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1240002501666
- Status
- Registered and active
- Builder
- PARSHIV BUILDERS & DEVELOPERS
- Location
- Palghar West, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 3 Dec 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- Delay so far
- 4 months
- Homes
- 28
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHREE DAYARAM RESIDENCY 1F: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHREE DAYARAM RESIDENCY 1F
Is SHREE DAYARAM RESIDENCY 1F registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE DAYARAM RESIDENCY 1F is registered as PR1240002501666 and its status is "Registered and active".
Where is SHREE DAYARAM RESIDENCY 1F?
SHREE DAYARAM RESIDENCY 1F by PARSHIV BUILDERS & DEVELOPERS is in Palghar West, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as PR1240002501666, per GharKundli's check of MahaRERA records.
When is possession of SHREE DAYARAM RESIDENCY 1F due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE DAYARAM RESIDENCY 1F in Palghar West, Palghar is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.
Does SHREE DAYARAM RESIDENCY 1F have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHREE DAYARAM RESIDENCY 1F?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARSHIV BUILDERS & DEVELOPERS.
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.