SHREE GURUDATTA HEIGHTS
by FUTURE BUILDCOM · Palghar West, Palghar
Registered on MahaRERA under PM1240002600157, and currently active. Its completion date has moved from December 2030 to April 2031, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHREE GURUDATTA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1240002600157
- Status
- Registered and active
- Builder
- FUTURE BUILDCOM
- Location
- Palghar West, Palghar · 401404
- Project type
- Mixed
- Registered on
- 17 Apr 2026
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- Delay so far
- 4 months
- Homes
- 136
- Sold or booked
- 2%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHREE GURUDATTA HEIGHTS: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHREE GURUDATTA HEIGHTS
Is SHREE GURUDATTA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE GURUDATTA HEIGHTS is registered as PM1240002600157 and its status is "Registered and active".
Where is SHREE GURUDATTA HEIGHTS?
SHREE GURUDATTA HEIGHTS by FUTURE BUILDCOM is in Palghar West, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as PM1240002600157, per GharKundli's check of MahaRERA records.
When is possession of SHREE GURUDATTA HEIGHTS due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE GURUDATTA HEIGHTS in Palghar West, Palghar is 30 April 2031 — 4 months later than 31 December 2030, the date given at registration.
Does SHREE GURUDATTA HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHREE GURUDATTA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is FUTURE BUILDCOM.
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.