KAKAD IMPERIAL
by NIRAJ KAKAD BUILDERS LLP · Bandra, MumbaiAlso near Sahar P and T Colony, Vileeparle East, Santacruz P and T Colony
Registered on MahaRERA under P51800009226. Status: Lapsed (registration period ended). Its completion date has moved from December 2019 to December 2021, 24 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2021) has passed.
GharKundli’s full report on KAKAD IMPERIAL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009226
- Status
- Lapsed (registration period ended)
- Builder
- NIRAJ KAKAD BUILDERS LLP
- Location
- Bandra, Mumbai · 400050
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 6
- Title report on file
- Not found
Kundli Watch
KAKAD IMPERIAL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KAKAD IMPERIAL
Is KAKAD IMPERIAL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAKAD IMPERIAL is registered as P51800009226 and its status is "Lapsed (registration period ended)".
Where is KAKAD IMPERIAL?
KAKAD IMPERIAL by NIRAJ KAKAD BUILDERS LLP is in Bandra, Mumbai (pincode 400050), near Sahar P and T Colony, Vileeparle East, Santacruz P and T Colony, Maharashtra, and is registered on MahaRERA as P51800009226, per GharKundli's check of MahaRERA records.
When is possession of KAKAD IMPERIAL due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KAKAD IMPERIAL in Bandra, Mumbai is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.
Does KAKAD IMPERIAL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in KAKAD IMPERIAL?
According to GharKundli's check of MahaRERA records (updated November 2026), KAKAD IMPERIAL has 12 homes in 1 tower registered on MahaRERA.
When was KAKAD IMPERIAL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAKAD IMPERIAL was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KAKAD IMPERIAL?
6 court cases are listed for KAKAD IMPERIAL on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KAKAD IMPERIAL?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRAJ KAKAD BUILDERS LLP.