Maaz Residency 15
by Mohseen Ali Maqsood Ali Khan · Padegaon, Aurangabad
Registered on MahaRERA under P51500022038. Status: Lapsed (registration period ended). Its completion date has moved from August 2023 to July 2025, 23 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2025) has passed.
GharKundli’s full report on Maaz Residency 15
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500022038
- Status
- Lapsed (registration period ended)
- Builder
- Mohseen Ali Maqsood Ali Khan
- Location
- Padegaon, Aurangabad · 431005
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- August 2023
- Latest completion date
- July 2025
- Delay so far
- 23 months
- Homes
- 16
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
Maaz Residency 15: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Maaz Residency 15
Is Maaz Residency 15 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Maaz Residency 15 is registered as P51500022038 and its status is "Lapsed (registration period ended)".
Where is Maaz Residency 15?
Maaz Residency 15 by Mohseen Ali Maqsood Ali Khan is in Padegaon, Aurangabad (pincode 431005), Maharashtra, and is registered on MahaRERA as P51500022038, per GharKundli's check of MahaRERA records.
When is possession of Maaz Residency 15 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Maaz Residency 15 in Padegaon, Aurangabad is 31 July 2025 — 23 months later than 1 August 2023, the date given at registration. That date has already passed.
Does Maaz Residency 15 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in Maaz Residency 15?
According to GharKundli's check of MahaRERA records (updated October 2026), Maaz Residency 15 has 16 homes in 1 tower registered on MahaRERA.
When was Maaz Residency 15 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Maaz Residency 15 was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Maaz Residency 15?
No court cases are listed for Maaz Residency 15 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Maaz Residency 15?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mohseen Ali Maqsood Ali Khan.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.