Grand Vista
by Anand Group Builders & Developers · Cidco Colony S.O (Nashik), Nashik
Registered on MahaRERA under PM1220002501846, and currently active. Its completion date has moved from December 2028 to April 2029, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Grand Vista
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1220002501846
- Status
- Registered and active
- Builder
- Anand Group Builders & Developers
- Location
- Cidco Colony S.O (Nashik), Nashik · 422009
- Project type
- Mixed
- Registered on
- 23 Dec 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- Delay so far
- 4 months
- Homes
- 26
- Sold or booked
- 6%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
Grand Vista: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Grand Vista
Is Grand Vista registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Vista is registered as PM1220002501846 and its status is "Registered and active".
Where is Grand Vista?
Grand Vista by Anand Group Builders & Developers is in Cidco Colony S.O (Nashik), Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as PM1220002501846, per GharKundli's check of MahaRERA records.
When is possession of Grand Vista due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Grand Vista in Cidco Colony S.O (Nashik), Nashik is 30 April 2029 — 4 months later than 31 December 2028, the date given at registration.
Does Grand Vista have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Grand Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Anand Group Builders & Developers, which has 1 other project registered on MahaRERA.
Other projects in pincode 422009
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.