by Ombuilders and develpers · Behind By Charch, Nashik 422009

What’s in the report? →

Possession date of Shiv Kunj (MahaRERA P51600047333): 30 April 2027, moved from 31 December 2024 (24 months later). It has 10 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600047333, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51600047333, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shiv Kunj?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shiv Kunj has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA18122518757)

    Reason the builder gave MahaRERA: “TECHNICAL”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shiv Kunj’s extension records on MahaRERA (P51600047333), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shiv Kunj

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600047333
Status
Registered and active
Builder
Ombuilders and develpers
Location
Behind By Charch, Nashik · 422009
Project type
Residential / Group Housing
Registered on
19 Oct 2022
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
10
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Shiv Kunj, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIV KUNJ APARTMENT0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SHIV KUNJ APARTMENT: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shiv Kunj every 1–2 months.

Shiv Kunj: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHIV KUNJ APARTMENT (5 floors, 10 units)
  • Car parking: 12 open
  • Land: 352 sq m (about 0.1 acres) · sanctioned built-up 914 sq m
  • Boundaries filed include: COLONY ROAD
  • Land, as filed: SURVEY NUMBER 889/5/1/1 2 3 4 /13 PLOT NO 13
  • Map: Get directions

The builder’s record and reviews

Ombuilders And Develpers has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 3 past the promised date (typically 18 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Shiv Kunj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shiv Kunj: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shiv Kunj

What is the possession date of Shiv Kunj?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shiv Kunj in Behind By Charch, Nashik is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shiv Kunj?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shiv Kunj's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shiv Kunj extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "TECHNICAL". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shiv Kunj?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shiv Kunj in Behind By Charch, Nashik is P51600047333.

Is Shiv Kunj registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj is registered as P51600047333 and its status is "Registered and active".

What is the current construction status of Shiv Kunj? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIV KUNJ APARTMENT is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shiv Kunj have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shiv Kunj safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj is registered on MahaRERA as P51600047333, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shiv Kunj?

Shiv Kunj is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shiv Kunj?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shiv Kunj: gharkundli.com/tools/property-cost-calculator

Has Shiv Kunj received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Shiv Kunj uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shiv Kunj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shiv Kunj's possession date changes?

The latest dates are on Shiv Kunj's MahaRERA page (P51600047333). GharKundli's Kundli Watch sends a free WhatsApp update on Shiv Kunj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shiv Kunj have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj has one building filed: SHIV KUNJ APARTMENT with 5 floors and 10 units.

How much parking does Shiv Kunj have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 open car parking spaces for Shiv Kunj.

How big is the land of Shiv Kunj?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj stands on 352 sq m of land (about 0.1 acres), with 914 sq m of sanctioned built-up area.

What is the track record of Shiv Kunj's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ombuilders And Develpers has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 3 past the promised date (typically 18 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shiv Kunj?

Google Maps has reviews of Shiv Kunj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shiv Kunj?

Shiv Kunj by Ombuilders and develpers is in Behind By Charch, Nashik, pincode 422009, Maharashtra, and is registered on MahaRERA as P51600047333, per GharKundli's check of MahaRERA records. Its boundaries filed there include COLONY ROAD. Its land is filed as SURVEY NUMBER 889/5/1/1 2 3 4 /13 PLOT NO 13. GharKundli lists all 443 MahaRERA projects in CIDCO Colony (422009).

How many flats are in Shiv Kunj, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj has 10 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Shiv Kunj registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Kunj was registered on MahaRERA on 19 October 2022. GharKundli did not find a title report on the land on file there.

Does Shiv Kunj have any legal issues or court cases?

No court cases are listed for Shiv Kunj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shiv Kunj?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ombuilders and develpers, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nashik →

Other projects in Nashik

All 443 projects in CIDCO Colony (422009) →

Other projects by Ombuilders and develpers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.