NAVNIWANT APARTMENT
by VISHWA CONSTRUCTION · Mouje Nashik, Nashik
Registered on MahaRERA under PR1220002502014, and currently active. Its completion date has moved from December 2031 to April 2032, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on NAVNIWANT APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1220002502014
- Status
- Registered and active
- Builder
- VISHWA CONSTRUCTION
- Location
- Mouje Nashik, Nashik · 422009
- Project type
- Residential / Group Housing
- Registered on
- 7 Jan 2026
- Completion date at registration
- December 2031
- Latest completion date
- April 2032
- Delay so far
- 4 months
- Homes
- 61
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
NAVNIWANT APARTMENT: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about NAVNIWANT APARTMENT
Is NAVNIWANT APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAVNIWANT APARTMENT is registered as PR1220002502014 and its status is "Registered and active".
Where is NAVNIWANT APARTMENT?
NAVNIWANT APARTMENT by VISHWA CONSTRUCTION is in Mouje Nashik, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as PR1220002502014, per GharKundli's check of MahaRERA records.
When is possession of NAVNIWANT APARTMENT due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NAVNIWANT APARTMENT in Mouje Nashik, Nashik is 30 April 2032 — 4 months later than 31 December 2031, the date given at registration.
Does NAVNIWANT APARTMENT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of NAVNIWANT APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VISHWA CONSTRUCTION, which has 1 other project registered on MahaRERA.
Other projects in pincode 422009
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.