BLISS
by KRIPA ELITE CORPORATION · Vikhroli East, MumbaiAlso near Tagore Nagar
Registered on MahaRERA under P51800031607. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
GharKundli’s full report on BLISS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031607
- Status
- Lapsed (registration period ended)
- Builder
- KRIPA ELITE CORPORATION
- Location
- Vikhroli East, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 31 Oct 2021
- Completion date at registration
- December 2025
- Homes
- 121
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Kundli Watch
BLISS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BLISS
Is BLISS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BLISS is registered as P51800031607 and its status is "Lapsed (registration period ended)".
Where is BLISS?
BLISS by KRIPA ELITE CORPORATION is in Vikhroli East, Mumbai (pincode 400083), near Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800031607, per GharKundli's check of MahaRERA records.
When is possession of BLISS due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BLISS in Vikhroli East, Mumbai is 31 December 2025. That date has already passed.
Does BLISS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), BLISS has 121 homes in 1 tower registered on MahaRERA.
When was BLISS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BLISS was registered on MahaRERA on 31 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on BLISS?
No court cases are listed for BLISS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KRIPA ELITE CORPORATION, which has 2 other projects registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.