TULSA PARK
by SHREE SHIVAM DEVELOPERS · Khadegolavali, Thane
Registered on MahaRERA under P51700005797. Status: Completed. Its completion date has moved from June 2021 to June 2024, 36 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on TULSA PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700005797
- Status
- Completed
- Builder
- SHREE SHIVAM DEVELOPERS
- Location
- Khadegolavali, Thane · 421306
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2024
- Delay so far
- 36 months
- Homes
- 120
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
TULSA PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TULSA PARK
Is TULSA PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TULSA PARK is registered as P51700005797 and its status is "Completed".
Where is TULSA PARK?
TULSA PARK by SHREE SHIVAM DEVELOPERS is in Khadegolavali, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700005797, per GharKundli's check of MahaRERA records.
When is possession of TULSA PARK due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TULSA PARK in Khadegolavali, Thane is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration.
Does TULSA PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in TULSA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), TULSA PARK has 120 homes in 4 towers registered on MahaRERA.
When was TULSA PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TULSA PARK was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TULSA PARK?
No court cases are listed for TULSA PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of TULSA PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE SHIVAM DEVELOPERS, which has 1 other project registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.