Skip to content
GharKundli

Rohini

by Thilayaparambil Kumaran Joshi · Shahapur, Thane

Registered on MahaRERA under P51700013602. Status: Completed. Its completion date has moved from June 2021 to December 2024, 42 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on Rohini

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700013602
Status
Completed
Builder
Thilayaparambil Kumaran Joshi
Location
Shahapur, Thane · 421604
Project type
Residential / Group Housing
Registered on
16 Oct 2017
Completion date at registration
June 2021
Latest completion date
December 2024
Delay so far
42 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Rohini: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Rohini

Is Rohini registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rohini is registered as P51700013602 and its status is "Completed".

Where is Rohini?

Rohini by Thilayaparambil Kumaran Joshi is in Shahapur, Thane (pincode 421604), Maharashtra, and is registered on MahaRERA as P51700013602, per GharKundli's check of MahaRERA records.

When is possession of Rohini due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rohini in Shahapur, Thane is 30 December 2024 — 42 months later than 30 June 2021, the date given at registration.

Does Rohini have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in Rohini?

According to GharKundli's check of MahaRERA records (updated November 2026), Rohini has 10 homes in 1 tower registered on MahaRERA.

When was Rohini registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rohini was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Rohini?

No court cases are listed for Rohini on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Rohini?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Thilayaparambil Kumaran Joshi.

Other projects in pincode 421604

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.