Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane

by MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Shirdhon, Thane

Registered on MahaRERA under P51700016820, and currently active. Its completion date has moved from March 2022 to July 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700016820
Status
Registered and active
Builder
MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY
Location
Shirdhon, Thane · 421204
Project type
Residential / Group Housing
Registered on
18 Jun 2018
Completion date at registration
March 2022
Latest completion date
July 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
9,227
Towers
78
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Kundli Watch

Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane

Is Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane is registered as P51700016820 and its status is "Registered and active".

Where is Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane?

Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane by MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY is in Shirdhon, Thane (pincode 421204), Maharashtra, and is registered on MahaRERA as P51700016820, per GharKundli's check of MahaRERA records.

When is possession of Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane in Shirdhon, Thane is 24 July 2027 — 60 months later than 25 March 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane?

According to GharKundli's check of MahaRERA records (updated November 2026), Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane has 9,227 homes in 78 towers registered on MahaRERA.

When was Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane was registered on MahaRERA on 18 June 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane?

No court cases are listed for Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY, which has 11 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.