by Aryak Associates · Sawantwadi, Sindhudurg
Registered on MahaRERA under P52900005744, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on ASHWAMEDH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900005744
- Status
- Registered and active
- Builder
- Aryak Associates
- Location
- Sawantwadi, Sindhudurg · 416510
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- April 2027
- Delay so far
- 96 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
ASHWAMEDH: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about ASHWAMEDH
Is ASHWAMEDH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHWAMEDH is registered as P52900005744 and its status is "Registered and active".
Where is ASHWAMEDH?
ASHWAMEDH by Aryak Associates is in Sawantwadi, Sindhudurg (pincode 416510), Maharashtra, and is registered on MahaRERA as P52900005744, per GharKundli's check of MahaRERA records.
When is possession of ASHWAMEDH due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASHWAMEDH in Sawantwadi, Sindhudurg is 30 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Does ASHWAMEDH have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in ASHWAMEDH?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHWAMEDH has 48 homes in 2 towers registered on MahaRERA.
When was ASHWAMEDH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ASHWAMEDH was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ASHWAMEDH?
No court cases are listed for ASHWAMEDH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ASHWAMEDH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aryak Associates.
Other projects in pincode 416510
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.