by VIJAY GANGARAM NAIK · Sawantwadi, Sindhudurg

Possession date of VRUKSHAVALLI B-4: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900046973, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VRUKSHAVALLI B-4?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VRUKSHAVALLI B-4 has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA06022619755)

    Reason the builder gave MahaRERA: “We have applied for extension of proposed date of completion from 31/12/2025 to 31/12/2026. Due to change in Building Sanction plans, part development work is carrying on, for this purpose we are requesting an extension till 31/12/2026.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VRUKSHAVALLI B-4’s extension records on MahaRERA (P52900046973), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VRUKSHAVALLI B-4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52900046973
Status
Registered and active
Builder
VIJAY GANGARAM NAIK
Location
Sawantwadi, Sindhudurg · 416510
Project type
Others
Registered on
26 Sep 2022
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
26
Sold or booked
66%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of VRUKSHAVALLI B-4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VRUKSHAVALLI B-4100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • VRUKSHAVALLI B-4: covers 7 floors

Latest CC order on MahaRERA: dated 13/06/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VRUKSHAVALLI B-4 every month.

VRUKSHAVALLI B-4: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Vijay Gangaram Naik has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of VRUKSHAVALLI B-4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VRUKSHAVALLI B-4: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VRUKSHAVALLI B-4

What is the possession date of VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VRUKSHAVALLI B-4 in Sawantwadi, Sindhudurg is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VRUKSHAVALLI B-4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VRUKSHAVALLI B-4's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VRUKSHAVALLI B-4 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We have applied for extension of proposed date of completion from 31/12/2025 to 31/12/2026. Due to change in Building Sanction plans, part development work is carrying on, for this purpose we are requesting an extension till 31/12/2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VRUKSHAVALLI B-4 in Sawantwadi, Sindhudurg is P52900046973.

Is VRUKSHAVALLI B-4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 is registered as P52900046973 and its status is "Registered and active".

What is the construction status of VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VRUKSHAVALLI B-4 is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does VRUKSHAVALLI B-4 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VRUKSHAVALLI B-4 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 is registered on MahaRERA as P52900046973, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does VRUKSHAVALLI B-4 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VRUKSHAVALLI B2 (P52900018490, possession 29 Mar 2024). Check that your agreement names the registration of your own wing.

How can I get updates if VRUKSHAVALLI B-4's possession date changes?

The latest dates are on VRUKSHAVALLI B-4's MahaRERA page (P52900046973). GharKundli's Kundli Watch sends a free WhatsApp update on VRUKSHAVALLI B-4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VRUKSHAVALLI B-4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 has one building filed: VRUKSHAVALLI B-4 with 7 floors and 29 units.

How much parking does VRUKSHAVALLI B-4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered and 8 open car parking spaces for VRUKSHAVALLI B-4.

How big is the land of VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 stands on 2,000 sq m of land (about 0.5 acres), with 3,054 sq m of sanctioned built-up area.

What is the track record of VRUKSHAVALLI B-4's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vijay Gangaram Naik has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VRUKSHAVALLI B-4?

Google Maps has reviews of VRUKSHAVALLI B-4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VRUKSHAVALLI B-4?

VRUKSHAVALLI B-4 by VIJAY GANGARAM NAIK is in Sawantwadi, Sindhudurg (pincode 416510), Maharashtra, and is registered on MahaRERA as P52900046973, per GharKundli's check of MahaRERA records.

How many homes are in VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 has 26 homes in 1 tower registered on MahaRERA, and 66% of them are sold or booked.

When was VRUKSHAVALLI B-4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VRUKSHAVALLI B-4 was registered on MahaRERA on 26 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on VRUKSHAVALLI B-4?

No court cases are listed for VRUKSHAVALLI B-4 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VRUKSHAVALLI B-4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIJAY GANGARAM NAIK, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Sindhudurg →

Other projects in pincode 416510

All 49 projects in Sawantwadi (416510) →

Other projects by VIJAY GANGARAM NAIK

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.