Possession due in 2027 · Sindhudurg
According to GharKundli's check of MahaRERA records, 15 housing projects in Sindhudurg have a MahaRERA completion date in 2027, out of 33 Sindhudurg projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Galaxy Residency Maitri Developers | Bidayewadi, Kalmath | 1 Jan 2027 | 1 Jan 2025 | 0 |
| VEENAS DREAM HOME VANITA GOVIND BHOSLE | Kasai | 28 Feb 2027 | 30 Dec 2023 | 2 |
| MANGALSIDDHI ARCADE MANGALA AND ASSOCIATES | Ganesh Nagar | 30 Mar 2027 | 12 Aug 2023 | 0 |
| SAI SAMARTH SANKUL A TYPE SAI SAMARTH ENTERPRISES | Kudal | 31 Mar 2027 | 31 Dec 2023 | 0 |
| KAMAT VISHWA - 2 Pranav Prakash Kamat | Near Kankavli College | 25 Apr 2027 | 25 Dec 2025 | 0 |
| ADITYASAGAR COMPLEX PHASE II Siddhesh Mahadeo Kanade | Sambhaji Chowk | 30 Apr 2027 | 31 Dec 2023 | 0 |
| ANAADIH SHRI DATTA PRABHAKAR KRISHNAJI PARAB | Kaskilwada | 30 Apr 2027 | 31 Dec 2025 | 0 |
| Anant Pride Unique Infra | Kankavali | 30 Apr 2027 | 30 Nov 2023 | 0 |
| RAMESHWAR COMPLEX RAMESHWAR CONSTRUCTIONS | Behind Nikhil Lunch Home | 30 Apr 2027 | 30 Jun 2024 | 2 |
| VRUKSHAVALLI B-4 VIJAY GANGARAM NAIK | Sawantwadi | 30 Apr 2027 | 31 Dec 2025 | 0 |
| Shree Sadan Shreeyash Builders and Developers proprietor Shriram Nivruti Thormote | Kankavli | 31 Jul 2027 | 31 Dec 2019 | 0 |
| AYAANS AMBARY Suman Developers | Malvan | 30 Oct 2027 | 30 Jun 2026 | 0 |
| PERTO DE GOA PHASE 4 Rushikesh Atul Labhshetwar | Niravade | 30 Oct 2027 | 31 Dec 2019 | 0 |
| Royal Enclave ELITE DEVELOPERS | Teli Ali | 30 Oct 2027 | 26 Jan 2026 | 0 |
| Prime Vista Umesh Sudhakar Sukhi | Kudal | 31 Dec 2027 | 30 Jun 2025 | 0 |
Other years in Sindhudurg: 2026 (5) · 2028 (5) · 2029 (2) · 2030 (4) · 2031 (1)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.