by Shreeyash Builders and Developers proprietor Shriram Nivruti Thormote · Kankavli, SindhudurgAlso near Kalmath

Possession date of Shree Sadan: 31 July 2027, moved from 31 December 2019 (87 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900013755, and currently active. Its completion date has moved from December 2019 to July 2027: 87 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Shree Sadan?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shree Sadan has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52900003934)

    Reason the builder gave MahaRERA:
    “We would like to request for an extension of project completion to a later time due to the following factors that were out of our control - Availability of Labours for construction work was limited with the appointed contractor. Limited ava…” Read the full reason“We would like to request for an extension of project completion to a later time due to the following factors that were out of our control - Availability of Labours for construction work was limited with the appointed contractor. Limited availability of funds reduced the pace of the work due to non booking of units in projects reducing the cash flow predicted from the sales. Above normal Rainfall in the season reduced the number of days available for carrying out construction activity.”
  3. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT52900012065)

    Reason the builder gave MahaRERA: “Revise project sanction as per new FSI rule. Due to above project 2 floor additional construction permission received from authority. We have required additional time to construct additional area of construction.”
  4. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52900015154)

    Reason the builder gave MahaRERA:
    “Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time,…” Read the full reason“Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time, in order to complete the Project. Hence this application is to extend the project along with the consent of allottees in the Project. Therefore, we kindly request you permit the extension of the project as per the date above.”
  5. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT52900019530)

    Reason the builder gave MahaRERA:
    “Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time,…” Read the full reason“Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time, in order to complete the Project. Hence this application.”
  6. 31 March 2026

    Extended at the builder's request (MahaRERA application EA06052501017)

    Reason the builder gave MahaRERA:
    “We are facing financial constraints due to low cash flow, as the flats have not yet been sold. This has further impacted our ability to progress as planned. As a result, additional time is necessary to address the delays and complete the re…” Read the full reason“We are facing financial constraints due to low cash flow, as the flats have not yet been sold. This has further impacted our ability to progress as planned. As a result, additional time is necessary to address the delays and complete the required tasks. Hence, additional time is required to address the delays, requesting you to grant us the same.”
  7. 31 March 2027

    Extended at the builder's request (MahaRERA application EA16022619853)

    Reason the builder gave MahaRERA:
    “The project is situated in a remote area, due to which there has been no sale of flats. This has resulted in low cash flow and financial constraints, affecting the progress of the project as originally planned. Owing to these financial diff…” Read the full reason“The project is situated in a remote area, due to which there has been no sale of flats. This has resulted in low cash flow and financial constraints, affecting the progress of the project as originally planned. Owing to these financial difficulties, we have availed a loan from the bank, which is presently in its final stage of processing. In view of the above circumstances, additional time is required to regularize the financial position and complete the remaining work of the project. Hence, additional time is required to address the delays, requesting you to grant us the same.”
  8. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shree Sadan’s extension records on MahaRERA (P52900013755), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Sadan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900013755
Status
Registered and active
Builder
Shreeyash Builders and Developers proprietor Shriram Nivruti Thormote
Location
Kankavli, Sindhudurg · 416602
Project type
Residential / Group Housing
Registered on
25 Oct 2017
Completion date at registration
December 2019
Latest completion date
July 2027
Delay so far
87 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
18
Sold or booked
6%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shree Sadan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shree Sadan100%100%85%0%

Commencement certificate (CC), as filed on MahaRERA

  • Shree Sadan: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Sadan every month.

Shree Sadan: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shree Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Sadan: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shree Sadan

What is the possession date of Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Sadan in Kankavli, Sindhudurg is 31 July 2027 — 87 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shree Sadan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Sadan's builder has filed on MahaRERA, the official one, is 31 July 2027, already 87 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shree Sadan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan's builder applied to MahaRERA to extend the completion date 6 times: to 30 December 2020, giving the reason "We would like to request for an extension of project completion to a later time due to the following factors that were out of our control - Availability of Labours for construction work was limited with the appointed contractor. Limited availability of funds reduced the pace of the work due to non booking of units in projects reducing the cash flow predicted from the sales. Above normal Rainfall in the season reduced the number of days available for carrying out construction activity."; to 31 March 2023, giving the reason "Revise project sanction as per new FSI rule. Due to above project 2 floor additional construction permission received from authority. We have required additional time to construct additional area of construction."; to 31 March 2024, giving the reason "Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time, in order to complete the Project. Hence this application is to extend the project along with the consent of allottees in the Project. Therefore, we kindly request you permit the extension of the project as per the date above."; to 31 March 2025, giving the reason "Due to the slowdown in the Real Estate market in Kankavli (where the said Project is situated), the expected revenue against the sales proceeds was very low. Hence making alternate arrangements for additional funds requires additional time, in order to complete the Project. Hence this application."; to 31 March 2026, giving the reason "We are facing financial constraints due to low cash flow, as the flats have not yet been sold. This has further impacted our ability to progress as planned. As a result, additional time is necessary to address the delays and complete the required tasks. Hence, additional time is required to address the delays, requesting you to grant us the same."; to 31 March 2027, giving the reason "The project is situated in a remote area, due to which there has been no sale of flats. This has resulted in low cash flow and financial constraints, affecting the progress of the project as originally planned. Owing to these financial difficulties, we have availed a loan from the bank, which is presently in its final stage of processing. In view of the above circumstances, additional time is required to regularize the financial position and complete the remaining work of the project. Hence, additional time is required to address the delays, requesting you to grant us the same.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Sadan in Kankavli, Sindhudurg is P52900013755.

Is Shree Sadan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan is registered as P52900013755 and its status is "Registered and active".

What is the construction status of Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shree Sadan is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Shree Sadan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Sadan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan is registered on MahaRERA as P52900013755, its completion date has moved 87 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shree Sadan's possession date changes?

The latest dates are on Shree Sadan's MahaRERA page (P52900013755). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Sadan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Sadan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan has one building filed: Shree Sadan with 5 floors and 18 units.

How big is the land of Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan stands on 625 sq m of land (about 0.2 acres), with 1,106 sq m of sanctioned built-up area.

Where can I read reviews of Shree Sadan?

Google Maps has reviews of Shree Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shree Sadan?

Shree Sadan by Shreeyash Builders and Developers proprietor Shriram Nivruti Thormote is in Kankavli, Sindhudurg (pincode 416602), near Kalmath, Maharashtra, and is registered on MahaRERA as P52900013755, per GharKundli's check of MahaRERA records. Its boundaries filed there include Gram Panchayat Road.

How many homes are in Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan has 18 homes in 1 tower registered on MahaRERA, and 6% of them are sold or booked.

When was Shree Sadan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadan was registered on MahaRERA on 25 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Shree Sadan?

No court cases are listed for Shree Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Shree Sadan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shreeyash Builders and Developers proprietor Shriram Nivruti Thormote.

All projects with possession due in 2027 in Sindhudurg →

Other projects in pincode 416602

All 39 projects in Kankavli (416602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.