by MAITRI DEVELOPERS · Kanak Nagar, SindhudurgAlso near Kalmath

Possession date of MAITRI GARDEN: 30 June 2028, moved from 30 December 2022 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900015714. Status: In abeyance (on hold by MahaRERA).

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MAITRI GARDEN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAITRI GARDEN has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT52900015175)

    Reason the builder gave MahaRERA:
    “1. The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. 2. We have been grappled with shortage of labour and a demand slump cha…” Read the full reason“1. The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. 2. We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. 3. The project site being situated at rural areas, the biggest challenge is to find skilled labour at a mass scale to assist in completion of work at a reasonable pace. 4. Due to unavailability of skilled labour and labour m…”
  3. 30 June 2028

    Extended at the builder's request (MahaRERA application EA26122519021)

    Reason the builder gave MahaRERA:
    “The promoter has obtained permissions for additional FSI at the site. This additional FSI is being consumed in Bldg. B as well as for construction of additional Bldg. C at the site. The revised permissions have been received in MAY 2025. •…” Read the full reason“The promoter has obtained permissions for additional FSI at the site. This additional FSI is being consumed in Bldg. B as well as for construction of additional Bldg. C at the site. The revised permissions have been received in MAY 2025. • The modifications required careful coordination with engineers, architects, and regulatory bodies to ensure that the structural integrity of the project remained uncompromised while adhering to quality and safety norms. • Additionally, the integration of the additional FSI in the existing Building B under construction requires adjustments in structural pl…”

Source: MAITRI GARDEN’s extension records on MahaRERA (P52900015714), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAITRI GARDEN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900015714
Status
In abeyance (on hold by MahaRERA)
Builder
MAITRI DEVELOPERS
Location
Kanak Nagar, Sindhudurg · 416602
Project type
Residential / Group Housing
Registered on
19 Mar 2018
Completion date at registration
December 2022
Latest completion date
June 2028
Delay so far
66 months
Homes
112
Sold or booked
3%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of MAITRI GARDEN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%100%100%
BUILDING B100%100%85%30%
BUILDING C0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers Commercial - Ground Floor + 1st Floor & 2nd To 7th Floor Residential
  • BUILDING B: covers Ground Floor + 1st to 7th Floor
  • BUILDING C: covers Ground Floor + 1st to 7th Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAITRI GARDEN every month.

MAITRI GARDEN: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (8 floors, 18 units) · BUILDING B (9 floors, 71 units) · BUILDING C (6 floors, 29 units)
  • Land: 3,600 sq m (about 0.9 acres) · sanctioned built-up 4,300 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAITRI GARDEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAITRI GARDEN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAITRI GARDEN

What is the possession date of MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAITRI GARDEN in Kanak Nagar, Sindhudurg is 30 June 2028 — 66 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MAITRI GARDEN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAITRI GARDEN's builder has filed on MahaRERA, the official one, is 30 June 2028, already 66 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAITRI GARDEN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2024, giving the reason "1. The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch showing down growth. 2. We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. 3. The project site being situated at rural areas, the biggest challenge is to find skilled labour at a mass scale to assist in completion of work at a reasonable pace. 4. Due to unavailability of skilled labour and labour m…"; to 30 June 2028, giving the reason "The promoter has obtained permissions for additional FSI at the site. This additional FSI is being consumed in Bldg. B as well as for construction of additional Bldg. C at the site. The revised permissions have been received in MAY 2025. • The modifications required careful coordination with engineers, architects, and regulatory bodies to ensure that the structural integrity of the project remained uncompromised while adhering to quality and safety norms. • Additionally, the integration of the additional FSI in the existing Building B under construction requires adjustments in structural pl…".

What is the RERA number of MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAITRI GARDEN in Kanak Nagar, Sindhudurg is P52900015714.

Is MAITRI GARDEN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN is registered as P52900015714 and its status is "In abeyance (on hold by MahaRERA)".

What is the construction status of MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does MAITRI GARDEN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MAITRI GARDEN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN is registered on MahaRERA as P52900015714, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAITRI GARDEN's possession date changes?

The latest dates are on MAITRI GARDEN's MahaRERA page (P52900015714). GharKundli's Kundli Watch sends a free WhatsApp update on MAITRI GARDEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAITRI GARDEN have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN has 3 buildings filed: BUILDING A with 8 floors and 18 units; BUILDING B with 9 floors and 71 units; BUILDING C with 6 floors and 29 units.

How big is the land of MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN stands on 3,600 sq m of land (about 0.9 acres), with 4,300 sq m of sanctioned built-up area.

Where can I read reviews of MAITRI GARDEN?

Google Maps has reviews of MAITRI GARDEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAITRI GARDEN?

MAITRI GARDEN by MAITRI DEVELOPERS is in Kanak Nagar, Sindhudurg (pincode 416602), near Kalmath, Maharashtra, and is registered on MahaRERA as P52900015714, per GharKundli's check of MahaRERA records.

How many homes are in MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN has 112 homes in 3 towers registered on MahaRERA, and 3% of them are sold or booked.

When was MAITRI GARDEN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAITRI GARDEN was registered on MahaRERA on 19 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on MAITRI GARDEN?

No court cases are listed for MAITRI GARDEN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MAITRI GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAITRI DEVELOPERS, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2028 in Sindhudurg →

Other projects in pincode 416602

All 39 projects in Kankavli (416602) →

Other projects by MAITRI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.